August forecast for Kentucky campus delivery

Company: TeraWulf - Project: Justified Data

Subject kind
facility timeline
Statement date
2026-11-04
Promised by
2028-03-31
Current status
stated

The claim, verbatim

TeraWulf's August forecast called for initial delivery in the second half of 2027 and full delivery in early 2028; the newer Fluor schedule extends beyond this forecast.

Source (primary)

TeraWulf Secures Google Credit Backstop for $19 Billion Anthropic AI Lease - TheEnergyMag (-, news_article)
View cached copy (2026-11-05)Live source ↗Archive.org ↗

Quote: “TeraWulf's August forecast, which called for initial delivery in the second half of 2027 and full delivery in early 2028”

How we checked this

This claim has not yet been checked assertion-by-assertion against its source. It carries a cited source and quote, but the deeper check has not run. When it does, the result appears here whatever it says.

Additional evidence

confirms TeraWulf Secures Google Credit Backstop for $19 Billion Anthropic AI Lease - TheEnergyMag

Quote: “TeraWulf's August forecast, which called for initial delivery in the second half of 2027 and full delivery in early 2028”

View cached copy (2026-11-05)Live source ↗Archive.org ↗

confirms TeraWulf Secures Google Credit Backstop for $19 Billion Anthropic AI Lease - TheEnergyMag

Quote: “TeraWulf’s August forecast, which called for initial delivery in the second half of 2027 and full delivery in early 2028”

View cached copy (2026-11-05)Live source ↗