jain.com

Fluor general contractor for Justified Data Campus

Company: TeraWulf - Project: Justified Data

Subject kind
partnership
Statement date
2026-10-06
Promised amount
4000000000.0 USD
Current status
stated

The claim, verbatim

TeraWulf is redeveloping a former aluminum smelter in Hawesville into a $4-billion-plus AI campus with Fluor as general contractor.

Source (primary)

TeraWulf Doubles Kentucky Data Center Power to 1 GW - Engineering News-Record (-, news_article)
View cached copy (2026-10-07)Live source ↗Archive.org ↗

Quote: “TeraWulf is redeveloping a former aluminum smelter there into a $4-billion-plus AI campus, with Fluor as general contractor”

How we checked this

Checked on October 9, 2026. The cited source supports every part of this claim.

The article states each of these facts about the Justified campus in Hawesville.

Confirmed in the source:

What we did: Read our cached copy of the publisher (https://www.enr.com/articles/63799-terawulf-doubles-kentucky-data-center-power-to-1-gw) in full (13,188 characters, retrieved October 7, 2026) and checked each assertion in the claim against it.

Additional evidence

confirms TeraWulf Doubles Kentucky Data Center Power to 1 GW - Engineering News-Record

Quote: “TeraWulf is redeveloping a former aluminum smelter there into a $4-billion-plus AI campus, with Fluor as general contractor”

View cached copy (2026-10-07)Live source ↗Archive.org ↗