Justified Data Campus ready-for-service schedule

Company: TeraWulf - Project: Justified Data

Subject kind
facility timeline
Statement date
2026-11-04
Promised by
2028-06-30
Current status
stated

The claim, verbatim

Under Fluor's milestone schedule, phased ready-for-service completions are expected to begin in late 2027 and continue through the second quarter of 2028.

Source (primary)

TeraWulf Secures Google Credit Backstop for $19 Billion Anthropic AI Lease - TheEnergyMag (-, news_article)
View cached copy (2026-11-05)Live source ↗Archive.org ↗

Quote: “phased completions ready for service are expected to begin in late 2027 and continue through the second quarter of 2028”

How we checked this

This claim has not yet been checked assertion-by-assertion against its source. It carries a cited source and quote, but the deeper check has not run. When it does, the result appears here whatever it says.

Additional evidence

confirms TeraWulf Secures Google Credit Backstop for $19 Billion Anthropic AI Lease - TheEnergyMag

Quote: “phased completions ready for service are expected to begin in late 2027 and continue through the second quarter of 2028”

View cached copy (2026-11-05)Live source ↗Archive.org ↗

confirms TeraWulf Lines Up Google Backstop for Anthropic’s Kentucky AI Campus - Unite.AI

Quote: “TeraWulf expects phased ready-for-service completions to begin in late 2027 and continue through the second quarter of 2028.”

View cached copy (2026-11-05)Live source ↗Archive.org ↗

confirms TeraWulf Secures Google Credit Backstop for $19 Billion Anthropic AI Lease - TheEnergyMag

Quote: “phased completions ready for service are expected to begin in late 2027 and continue through the second quarter of 2028”

View cached copy (2026-11-05)Live source ↗