Campus repurposes Century Aluminum site infrastructure
Company: TeraWulf - Project: Justified Data
The claim, verbatim
TeraWulf will repurpose the former Century Aluminum smelter site and reuse its existing 482 MW of transmission infrastructure
Source (primary)
Kentucky Clears 482 MW AI Power Deal for TeraWulf’s Anthropic Campus - TheEnergyMag (-, news_article)
View cached copy (2026-09-01)Live source ↗
Quote: “The facility repurposes the former Century Aluminum Hawesville site and its existing transmission infrastructure.”
How we checked this
Checked on September 18, 2026. The cited source supports every part of this claim.
The article says the campus reuses the former Century Aluminum Hawesville smelter site and its roughly 482 MW of existing transmission capacity.
Confirmed in the source:
- The campus occupies the former Century Aluminum smelter site
- About 482 MW of transmission capacity remained in place at the site
- The project repurposes the site's existing transmission infrastructure
What we did: Read our cached copy of the publisher (https://theminermag.com/news/market-news/kentucky-482-mw-power-deal-terawulf-ai-data-center) in full (5,325 characters, retrieved September 1, 2026) and checked each assertion in the claim against it.
Additional evidence
confirms Kentucky Clears 482 MW AI Power Deal for TeraWulf’s Anthropic Campus - TheEnergyMag
Quote: “The facility repurposes the former Century Aluminum Hawesville site and its existing transmission infrastructure.”