Anthropic 20-year lease at Hawesville, KY campus
Company: TeraWulf
The claim, verbatim
In July 2026, TeraWulf subsidiary Raylan Data LLC entered into a 20-year lease with Anthropic to provide approximately 401 MW of critical IT load for HPC operations at the company's Hawesville, Kentucky data center campus.
Source (primary)
TeraWulf 8-K filed 2026-11-04 (SEC EDGAR, sec_filing)
View cached copy (2026-11-05)Live source ↗
Quote: “in July 2026, the Company’s subsidiary Raylan Data LLC (“Raylan”) entered into a 20-year lease agreement with Anthropic, PBC (“Anthropic”), as tenant, to provide Anthropic with approximately 401 MW of critical IT load for high-performance computing (“HPC”) operations at the Company’s data center campus located in Hawesville, Kentucky.”
How we checked this
This claim has not yet been checked assertion-by-assertion against its source. It carries a cited source and quote, but the deeper check has not run. When it does, the result appears here whatever it says.
Additional evidence
confirms TeraWulf 8-K filed 2026-11-04
Quote: “in July 2026, the Company’s subsidiary Raylan Data LLC (“Raylan”) entered into a 20-year lease agreement with Anthropic, PBC (“Anthropic”), as tenant, to provide Anthropic with approximately 401 MW of critical IT load for high-performance computing (“HPC”) operations at the Company’s data center campus located in Hawesville, Kentucky.”