jain.com

Justified Data campus development timeline

Company: TeraWulf - Project: Justified Data

Subject kind
facility timeline
Statement date
2026-07-05
Promised by
2028-03-31
Current status
stated

The claim, verbatim

Initial capacity at Justified Data is expected to be placed into service during the second half of 2027, with the campus ramping to the full 401 MW by early 2028

Source (primary)

terawulf 8-K exhibit (tm2619468d1_ex99-1.htm) (SEC EDGAR (8-K Ex), press_release)
View cached copy (2026-09-04)Live source ↗

Quote: “Initial capacity is expected to be placed into service during the second half of 2027, with the campus ramping to the full 401 MW by early 2028”

How we checked this

This claim has not yet been checked assertion-by-assertion against its source. It carries a cited source and quote, but the deeper check has not run. When it does, the result appears here whatever it says.

Additional evidence

confirms terawulf 8-K exhibit (tm2619468d1_ex99-1.htm)

Quote: “Initial capacity is expected to be placed into service during the second half of 2027, with the campus ramping to the full 401 MW by early 2028”

View cached copy (2026-09-04)Live source ↗