Justified Data campus development timeline

Company: TeraWulf - Project: Justified Data

Subject kind
facility timeline
Statement date
2026-07-05
Promised by
2028-03-31
Current status
stated

The claim, verbatim

Initial capacity at Justified Data is expected to be placed into service during the second half of 2027, with the campus ramping to the full 401 MW by early 2028

Source (primary)

terawulf 8-K exhibit (tm2619468d1_ex99-1.htm) (SEC EDGAR (8-K Ex), press_release)
View cached copy (2026-09-04)Live source ↗

Quote: “Initial capacity is expected to be placed into service during the second half of 2027, with the campus ramping to the full 401 MW by early 2028”

How we checked this

Checked on September 19, 2026. The cited source supports every part of this claim.

The document states initial capacity is expected in the second half of 2027 with the campus ramping to full 401 MW by early 2028.

Confirmed in the source:

What we did: Read our cached copy of SEC EDGAR (8-K Ex) (https://www.sec.gov/Archives/edgar/data/1083301/000110465926080583/tm2619468d1_ex99-1.htm) in full (10,258 characters, retrieved September 4, 2026) and checked each assertion in the claim against it.

Additional evidence

confirms terawulf 8-K exhibit (tm2619468d1_ex99-1.htm)

Quote: “Initial capacity is expected to be placed into service during the second half of 2027, with the campus ramping to the full 401 MW by early 2028”