Campus reaches full power capacity

Company: TeraWulf - Project: Justified Data

Subject kind
facility timeline
Statement date
2026-08-24
Promised by
2028-01-01
Current status
stated

The claim, verbatim

The Justified Data Campus is expected to reach full capacity in early 2028

Source (primary)

Kentucky Clears 482 MW AI Power Deal for TeraWulf’s Anthropic Campus - TheEnergyMag (-, news_article)
View cached copy (2026-09-01)Live source ↗

Quote: “Delivery is scheduled to begin in late 2027 and reach full capacity in early 2028, according to TeraWulf's SEC filing on Monday.”

How we checked this

Checked on September 18, 2026. The cited source supports every part of this claim.

The article says delivery is scheduled to reach full capacity in early 2028, citing TeraWulf's SEC filing.

Confirmed in the source:

What we did: Read our cached copy of the publisher (https://theminermag.com/news/market-news/kentucky-482-mw-power-deal-terawulf-ai-data-center) in full (5,325 characters, retrieved September 1, 2026) and checked each assertion in the claim against it.

Additional evidence

confirms Kentucky Clears 482 MW AI Power Deal for TeraWulf’s Anthropic Campus - TheEnergyMag

Quote: “Delivery is scheduled to begin in late 2027 and reach full capacity in early 2028, according to TeraWulf's SEC filing on Monday.”

View cached copy (2026-09-01)Live source ↗