jain.com

Justified Data delivery target

Company: TeraWulf

Subject kind
facility timeline
Statement date
2026-05-14
Promised by
2027-12-31
Current status
stated

The claim, verbatim

The Justified Data campus in Hawesville, KY is targeting delivery in the second half of 2027.

Source (primary)

Q1 2026 Earnings Update Presentation (IR page (investors.terawulf.com), ir_presentation)
View cached copy (2026-11-05)Live source ↗Archive.org ↗

Quote: “Targeting 2H 2027 delivery”

How we checked this

This claim has not yet been checked assertion-by-assertion against its source. It carries a cited source and quote, but the deeper check has not run. When it does, the result appears here whatever it says.

Additional evidence

confirms Q1 2026 Earnings Update Presentation

Quote: “Targeting 2H 2027 delivery”

View cached copy (2026-11-05)Live source ↗Archive.org ↗