Anthropic 20-year lease, ~401 MW

Company: TeraWulf - Project: Justified Data

Subject kind
customer
Statement date
2026-11-09
Promised amount
401.0 MW
Current status
stated

The claim, verbatim

In July 2026, TeraWulf subsidiary Raylan Data LLC entered into a 20-year lease with Anthropic covering approximately 401 MW of critical IT load across data center buildings CB-1, CB-2 and CB-3 at the Justified Data Campus.

Source (primary)

Google Could Take a Stake in Bitcoin Miner TeraWulf's $19.1B AI Project if Anthropic Defaults - KuCoin (-, news_article)
View cached copy (2026-11-14)Live source ↗Archive.org ↗

Quote: “Its subsidiary, Raylan Data LLC, entered into a 20-year lease with Anthropic in July 2026, covering approximately 401 MW of critical IT load across three data center buildings identified as CB-1, CB-2, and CB-3.”

How we checked this

Attempted on November 17, 2026. We could not read enough of the cited source to check this claim.

The verification run did not return a result for this claim (claude -p exit 1: b'').

What we did: Read our cached copy of the publisher (https://www.kucoin.com/blog/google-terawulf-anthropic-ai-project) in full (26,741 characters, retrieved November 14, 2026) and checked each assertion in the claim against it.

Additional evidence

confirms Google Could Take a Stake in Bitcoin Miner TeraWulf's $19.1B AI Project if Anthropic Defaults - KuCoin

Quote: “Its subsidiary, Raylan Data LLC, entered into a 20-year lease with Anthropic in July 2026, covering approximately 401 MW of critical IT load across three data center buildings identified as CB-1, CB-2, and CB-3.”

View cached copy (2026-11-14)Live source ↗Archive.org ↗