jain.com

Expected capital investment in initial data halls and site development

Company: TeraWulf - Project: Justified Data

Subject kind
financing
Statement date
2026-08-24
Promised amount
4000000000.0 USD
Current status
stated

The claim, verbatim

TeraWulf is expected to invest between 4 billion and 4.5 billion USD in the initial data halls and site development based on development costs of 10-12 million USD per MW

Source (primary)

Kentucky regulators approve 482 MW power deal for TeraWulf’s Justified Data Campus - W.Media (-, news_article)
View cached copy (2026-09-01)Live source ↗

Quote: “The PSC estimates that, based on current expected development costs of between US$ 10 million and US$ 12 million per MW of critical IT load, TeraWulf will invest between US$ 4 billion and US$ 4.5 billion in the initial data halls and site development.”

How we checked this

This claim has not yet been checked assertion-by-assertion against its source. It carries a cited source and quote, but the deeper check has not run. When it does, the result appears here whatever it says.

Additional evidence

confirms Kentucky regulators approve 482 MW power deal for TeraWulf’s Justified Data Campus - W.Media

Quote: “The PSC estimates that, based on current expected development costs of between US$ 10 million and US$ 12 million per MW of critical IT load, TeraWulf will invest between US$ 4 billion and US$ 4.5 billion in the initial data halls and site development.”

View cached copy (2026-09-01)Live source ↗