20-year Anthropic data center agreement
Company: TeraWulf - Project: Justified Data
The claim, verbatim
TeraWulf has a 20-year partnership with Anthropic for approximately 400 megawatts of capacity carrying $19 billion in contracted revenue.
Source (primary)
TeraWulf Drops 4% on Profit Taking After a 44% YTD Run; Applied Digital Falls 3%, IREN Pulls Back - 24/7 Wall St. (-, news_article)
View cached copy (2026-09-11)Live source ↗Archive.org ↗
Quote: “a 20-year deal with Anthropic for roughly 400 megawatts carrying $19 billion in contracted revenue”
How we checked this
Checked on September 20, 2026. The cited source supports every part of this claim.
The document states verbatim the 20-year Anthropic deal for roughly 400 megawatts carrying $19 billion in contracted revenue.
Confirmed in the source:
- TeraWulf has a 20-year partnership with Anthropic
- the deal covers approximately 400 megawatts of capacity
- the deal carries $19 billion in contracted revenue
What we did: Read our cached copy of the publisher (https://247wallst.com/investing/2026/09/10/terawulf-drops-4-on-profit-taking-after-a-44-ytd-run-applied-digital-falls-3-iren-pulls-back/) in full (11,900 characters, retrieved September 11, 2026) and checked each assertion in the claim against it.
Additional evidence
confirms TeraWulf Drops 4% on Profit Taking After a 44% YTD Run; Applied Digital Falls 3%, IREN Pulls Back - 24/7 Wall St.
Quote: “a 20-year deal with Anthropic for roughly 400 megawatts carrying $19 billion in contracted revenue”