jain.com

Justified Data delivery 2H 2027

Company: TeraWulf - Project: Justified Data

Subject kind
facility timeline
Statement date
2026-02-26
Promised by
2027-12-31
Promised amount
480.0 MW
Current status
stated

The claim, verbatim

Justified Data 480 MW Hawesville, KY campus is targeting delivery in 2H 2027, with hyperscaler diligence underway.

Source (primary)

Q4 Earnings Update Presentation (IR page (investors.terawulf.com), ir_presentation)
View cached copy (2026-10-13)Live source ↗Archive.org ↗

Quote: “Targeting 2H 2027 delivery”

How we checked this

Checked on October 15, 2026. The cited source supports every part of this claim.

The Justified Data slide gives the 480 MW Hawesville, KY campus and the 2H 2027 delivery target. It also says hyperscalers are engaged and diligence is underway.

Confirmed in the source:

What we did: Read our cached copy of IR page (investors.terawulf.com) (https://d1io3yog0oux5.cloudfront.net/_513c80c486e62e4bdb70115ded3782f5/terawulf/db/2396/23307/pdf/TeraWulf_Q4_2025_Investor_Presentation_%28Feb_2026%29.pdf) in full (28,069 characters, retrieved October 13, 2026) and checked each assertion in the claim against it.

Additional evidence

confirms Q4 Earnings Update Presentation

Quote: “Targeting 2H 2027 delivery”

View cached copy (2026-10-13)Live source ↗Archive.org ↗