jain.com

Hawesville Big Rivers transmission charge

Company: TeraWulf - Project: Justified Data

Subject kind
partnership
Statement date
2026-10-05
Promised amount
10000000.0 USD
Current status
stated

The claim, verbatim

TeraWulf will pay Big Rivers a transmission charge of more than $10 million per year under its OATT.

Source (primary)

TeraWulf Expands Muskie to 1 GW and SpaceX Mulls TSMC for Terafab - Yahoo Finance (-, news_article)
View cached copy (2026-10-06)Live source ↗Archive.org ↗

Quote: “Teror Wolf will also pay Big Rivers a transmission charge pursuant to the Big Rivers federally approved open access transmission tariff of more than $10 million per year”

How we checked this

Checked on October 13, 2026. The cited source supports every part of this claim.

The transcript quotes TeraWulf's Kentucky power plan for the Hawesville site, which says TeraWulf will pay Big Rivers a transmission charge of more than $10 million per year under Big Rivers' federally approved open access transmission tariff.

Confirmed in the source:

What we did: Read our cached copy of the publisher (https://finance.yahoo.com/video/terawulf-expands-muskie-1-gw-201417020.html) in full (40,989 characters, retrieved October 6, 2026) and checked each assertion in the claim against it.

Additional evidence

confirms TeraWulf Expands Muskie to 1 GW and SpaceX Mulls TSMC for Terafab - Yahoo Finance

Quote: “Teror Wolf will also pay Big Rivers a transmission charge pursuant to the Big Rivers federally approved open access transmission tariff of more than $10 million per year”

View cached copy (2026-10-06)Live source ↗Archive.org ↗

confirms TeraWulf doubles Muskie power to 1 GW - Yahoo Finance

Quote: “Terror Wolf will also pay big rivers a transmission charge pursuant to the big rivers federally approved open access transmission tariff of more than $10 million per per year”

View cached copy (2026-10-06)Live source ↗