TeraWulf entered a definitive engineering, procurement and construction agreement with Fluor Enterprises for the three data center buildings. It covers engineering, procurement, construction, testing and commissioning, with defined delivery milestones and cost-management provisions.

Source (primary)

Google Could Take a Stake in Bitcoin Miner TeraWulf's $19.1B AI Project if Anthropic Defaults - KuCoin (-, news_article)
View cached copy (2026-11-14)Live source ↗Archive.org ↗

Quote: “The November 4 announcement also included a definitive engineering, procurement, and construction (EPC) agreement with Fluor Enterprises for the three data center buildings.”

How we checked this

Attempted on November 17, 2026. We could not read enough of the cited source to check this claim.

The verification run did not return a result for this claim (claude -p exit 1: b'').

What we did: Read our cached copy of the publisher (https://www.kucoin.com/blog/google-terawulf-anthropic-ai-project) in full (26,741 characters, retrieved November 14, 2026) and checked each assertion in the claim against it.

Additional evidence

confirms Google Could Take a Stake in Bitcoin Miner TeraWulf's $19.1B AI Project if Anthropic Defaults - KuCoin

Quote: “The November 4 announcement also included a definitive engineering, procurement, and construction (EPC) agreement with Fluor Enterprises for the three data center buildings.”