jain.com

Fluor definitive EPC agreement for Justified

Company: TeraWulf

Subject kind
partnership
Statement date
2026-11-05
Promised amount
3.0 buildings
Current status
stated

The claim, verbatim

TeraWulf signed a definitive EPC agreement with Fluor covering engineering, procurement, and construction for three data center buildings at Justified, building on the limited notice to proceed announced in March 2026.

Source (primary)

Google to serve as credit backstop for TeraWulf data center in Kentucky (-, news_article)
View cached copy (2026-11-06)Live source ↗Archive.org ↗

Quote: “it has signed a definitive EPC agreement with Fluor covering engineering, procurement, and construction activities for three data center buildings at Justified, building on the limited notice to proceed announced in March 2026”

How we checked this

This claim has not yet been checked assertion-by-assertion against its source. It carries a cited source and quote, but the deeper check has not run. When it does, the result appears here whatever it says.

Additional evidence

confirms Google to serve as credit backstop for TeraWulf data center in Kentucky

Quote: “it has signed a definitive EPC agreement with Fluor covering engineering, procurement, and construction activities for three data center buildings at Justified, building on the limited notice to proceed announced in March 2026”

View cached copy (2026-11-06)Live source ↗Archive.org ↗

confirms Google to serve as credit backstop for TeraWulf data center in Kentucky - Data Center Dynamics

Quote: “it has signed a definitive EPC agreement with Fluor covering engineering, procurement, and construction activities for three data center buildings at Justified, building on the limited notice to proceed announced in March 2026.”

View cached copy (2026-11-06)Live source ↗Archive.org ↗