Fluor EPC agreement for Justified Data Campus
Company: TeraWulf - Project: Justified Data
The claim, verbatim
TeraWulf signed a definitive engineering, procurement and construction agreement with Fluor Enterprises covering three buildings at its Justified Data Campus in Hawesville, Kentucky, expanding work begun under a limited notice to proceed announced in March.
Source (primary)
TeraWulf Secures Google Credit Backstop for $19 Billion Anthropic AI Lease - TheEnergyMag (-, news_article)
View cached copy (2026-11-05)Live source ↗Archive.org ↗
Quote: “signed a definitive engineering, procurement and construction agreement with Fluor Enterprises covering three buildings at its Justified Data Campus in Hawesville, Kentucky”
How we checked this
This claim has not yet been checked assertion-by-assertion against its source. It carries a cited source and quote, but the deeper check has not run. When it does, the result appears here whatever it says.
Additional evidence
confirms TeraWulf Secures Google Credit Backstop for $19 Billion Anthropic AI Lease - TheEnergyMag
Quote: “signed a definitive engineering, procurement and construction agreement with Fluor Enterprises covering three buildings at its Justified Data Campus in Hawesville, Kentucky”
confirms Google backs TeraWulf’s $19 billion Anthropic lease with credit support - Cryptonews.net
Quote: “TeraWulf finalized a definitive engineering, procurement, and construction agreement with Fluor Enterprises, Inc.”
confirms TeraWulf gets Google credit support to develop data center campus - TradingView
Quote: “it signed a definitive engineering, procurement and construction agreement with Fluor FLR for the development of the campus”
confirms TeraWulf Secures Google Credit Support for Kentucky Data Center Campus - citybiz
Quote: “TeraWulf also signed a definitive engineering, procurement and construction agreement with Fluor to develop the campus.”
confirms TeraWulf Secures Google Credit Backstop for $19 Billion Anthropic AI Lease - TheEnergyMag
Quote: “signed a definitive engineering, procurement and construction agreement with Fluor Enterprises covering three buildings at its Justified Data Campus in Hawesville, Kentucky”