Hawesville available transmission capability

Company: TeraWulf

Subject kind
facility capacity
Statement date
2026-11-05
Promised amount
482.0 MW
Current status
stated

The claim, verbatim

The Kentucky commission found that about 482 MW of transmission capability remains available at the former smelter site, where the delivery point is connected to five 161-kV Big Rivers circuits.

Source (primary)

Fluor Wins EPC Contract for $4B-Plus Terawulf Data Center Complex in Kentucky - Engineering News-Record (-, news_article)
View cached copy (2026-11-06)Live source ↗Archive.org ↗

Quote: “The commission found that about 482 MW of transmission capability remains available at the former smelter site, where the delivery point is connected to five 161-kV Big Rivers circuits.”

How we checked this

This claim has not yet been checked assertion-by-assertion against its source. It carries a cited source and quote, but the deeper check has not run. When it does, the result appears here whatever it says.

Additional evidence

confirms Fluor Wins EPC Contract for $4B-Plus Terawulf Data Center Complex in Kentucky - Engineering News-Record

Quote: “The commission found that about 482 MW of transmission capability remains available at the former smelter site, where the delivery point is connected to five 161-kV Big Rivers circuits.”