Big Rivers substation modification reimbursement obligation

Company: TeraWulf - Project: Justified Data

Subject kind
financing
Statement date
2026-08-25
Promised amount
11.2 USD
Current status
stated

The claim, verbatim

TeraWulf agreed to reimburse Big Rivers for substation modifications with a net obligation of approximately $11.2 million after $600,000 equipment credit

Source (primary)

TeraWulf Advances $4B Data Center at Former Kentucky Smelter - Engineering News-Record (-, news_article)
View cached copy (2026-09-01)Live source ↗

Quote: “TeraWulf disclosed in its filing that it agreed to reimburse Big Rivers for substation modifications, with a net obligation of about $11.2 million after a $600,000 credit for electrical equipment”

How we checked this

This claim has not yet been checked assertion-by-assertion against its source. It carries a cited source and quote, but the deeper check has not run. When it does, the result appears here whatever it says.

Additional evidence

confirms TeraWulf Advances $4B Data Center at Former Kentucky Smelter - Engineering News-Record

Quote: “TeraWulf disclosed in its filing that it agreed to reimburse Big Rivers for substation modifications, with a net obligation of about $11.2 million after a $600,000 credit for electrical equipment”

View cached copy (2026-09-01)Live source ↗