jain.com

Big Rivers substation modification reimbursement obligation

Company: TeraWulf - Project: Justified Data

Subject kind
financing
Statement date
2026-08-25
Promised amount
11.2 USD
Current status
stated

The claim, verbatim

TeraWulf agreed to reimburse Big Rivers for substation modifications with a net obligation of approximately $11.2 million after $600,000 equipment credit

Source (primary)

TeraWulf Advances $4B Data Center at Former Kentucky Smelter - Engineering News-Record (-, news_article)
View cached copy (2026-09-01)Live source ↗

Quote: “TeraWulf disclosed in its filing that it agreed to reimburse Big Rivers for substation modifications, with a net obligation of about $11.2 million after a $600,000 credit for electrical equipment”

How we checked this

Checked on September 15, 2026. The cited source supports every part of this claim.

The article reports TeraWulf's disclosure of an agreement to reimburse Big Rivers for substation modifications, with a net obligation of about $11.2 million after a $600,000 equipment credit.

Confirmed in the source:

What we did: Read our cached copy of the publisher (https://www.enr.com/articles/63556-terawulf-advances-4b-data-center-at-former-kentucky-smelter) in full (11,913 characters, retrieved September 1, 2026) and checked each assertion in the claim against it.

Additional evidence

confirms TeraWulf Advances $4B Data Center at Former Kentucky Smelter - Engineering News-Record

Quote: “TeraWulf disclosed in its filing that it agreed to reimburse Big Rivers for substation modifications, with a net obligation of about $11.2 million after a $600,000 credit for electrical equipment”

View cached copy (2026-09-01)Live source ↗