August forecast for full delivery

Company: TeraWulf

Subject kind
facility timeline
Statement date
2026-11-04
Promised by
2028-03-31
Current status
stated

The claim, verbatim

TeraWulf's August forecast called for full delivery of the Kentucky campus in early 2028, which the Fluor schedule now extends beyond.

Source (primary)

TeraWulf Secures Google Credit Backstop for $19 Billion Anthropic AI Lease - TheEnergyMag (-, news_article)
View cached copy (2026-11-06)Live source ↗Archive.org ↗

Quote: “full delivery in early 2028”