jain.com

Authorized electric service capacity

Company: TeraWulf - Project: Justified Data

Subject kind
facility capacity
Statement date
2026-08-24
Promised amount
482.0 MW
Current status
stated

The claim, verbatim

The power agreement allows up to 482 megawatts of electric service for the Justified Data Campus.

Source (primary)

PSC approves power agreement for TeraWulf data campus - Spectrum News (-, news_article)
View cached copy (2026-09-01)Live source ↗

Quote: “The agreement allows up to 482 megawatts of electric service for the campus.”

How we checked this

This claim has not yet been checked assertion-by-assertion against its source. It carries a cited source and quote, but the deeper check has not run. When it does, the result appears here whatever it says.

Additional evidence

confirms PSC approves power agreement for TeraWulf data campus - Spectrum News

Quote: “The agreement allows up to 482 megawatts of electric service for the campus.”

View cached copy (2026-09-01)Live source ↗