jain.com

NC-1

Project of WhiteFiber

Kind
datacenter
Location
805 Island Drive, Madison, NC
County
Rockingham
State/region
NC
Country
US
Status
announced

Capacity

What has actually been delivered, against what has been promised. Each figure links to the statement it came from.

StageCapacityAs ofSource
Energized power flowing today40 MW2026-08-12NC-1 site active deployment
Contracted a customer is on the hook99 MW2025-08-07Duke Energy capacity agreement for NC-1
Under construction40 MW2026-05-26NC-1 Phase I Data Center Capacity
Permitted--
Interconnect approved utility has agreed to deliver--
Interconnect requested in a queue, nothing approved--
Announced a press-release figure300 MW2026-08-21NC-1 potential to scale to 300 gross megawatts

Who has claimed this site

Capacity commitments in the order they were announced. A commitment that ended shows why.

2025-12-17
Nscale - tenant ยท 10-year term source

Claims about this project

2025-07-10 - delayed
NC-1 initial 24 MW completion 24.0 MW. Promised by 2026-03-31.
2025-07-10 - delayed
Duke Energy 40 MW capacity commitment 40.0 MW. Promised by 2026-04-01.
2025-07-10 - stated
Duke Energy 99 MW capacity commitment 99.0 MW. Promised by 2029-05-16.
2025-07-10 - delayed
Duke Energy 24 MW capacity commitment 24.0 MW. Promised by 2025-09-01.
2025-07-10 - delayed
NC-1 revenue start. Promised by 2026-05-01.
2025-07-22 - delayed
Duke Energy - 24 MW 24.0 MW. Promised by 2025-09-01.
2025-07-22 - delayed
NC-1 revenue start. Promised by 2026-05-01.
2025-07-22 - stated
2025-07-22 - delayed
Duke Energy - 40 MW 40.0 MW. Promised by 2026-04-01.
2025-07-22 - stated
2025-07-22 - stated
Duke Energy - 99 MW 99.0 MW. Promised by 2029-05-16.
2025-07-28 - delayed
NC-1 initial capacity completion 24.0 MW. Promised by 2026-03-31.
2025-07-28 - delayed
NC-1 revenue generation start date. Promised by 2026-05-31.
2025-07-28 - delayed
Duke Energy capacity agreement - Phase 1 24.0 MW. Promised by 2025-09-01.
2025-07-28 - delayed
NC-1 24 MW energization in Q1 2026 24.0 MW. Promised by 2026-03-31.
2025-07-28 - stated
Duke Energy capacity agreement - Phase 3 99.0 MW. Promised by 2029-05-16.
2025-07-28 - delayed
NC-1 40 MW cumulative capacity by Q2 2026 40.0 MW. Promised by 2026-06-30.
2025-07-28 - delayed
Duke Energy capacity agreement - Phase 2 40.0 MW. Promised by 2026-04-01.
2025-07-31 - stated
Duke Energy capacity commitment - 99 MW milestone 99.0 MW. Promised by 2029-05-16.
2025-07-31 - delayed
Duke Energy capacity commitment - 24 MW milestone 24.0 MW. Promised by 2025-09-01.
2025-07-31 - delayed
NC-1 initial capacity operational date 24.0 MW. Promised by 2026-03-31.
2025-07-31 - delayed
Duke Energy capacity commitment - 40 MW milestone 40.0 MW. Promised by 2026-04-01.
2025-08-07 - delayed
NC-1 initial capacity completion 24.0 MW. Promised by 2026-03-31.
2025-08-07 - stated
2025-08-07 - stated
Duke Energy capacity agreement for NC-1 99.0 MW. Promised by 2029-05-16.
2025-08-07 - delayed
NC-1 revenue generation start. Promised by 2026-05-31.
2025-12-17 - delayed
Billing commencement for first 20 MW phase 20.0 MW. Promised by 2026-04-30.
2025-12-17 - delayed
Billing commencement for second 20 MW phase 20.0 MW. Promised by 2026-05-30.
2025-12-17 - stated
2026-03-25 - delayed
Duke Energy 40 MW service target for NC-1 40.0 MW. Promised by 2026-04-01.
2026-03-25 - stated
Duke Energy 99 MW service target for NC-1 99.0 MW. Promised by 2029-05-16.
2026-03-25 - stated
2026-03-25 - delayed
Nscale 40 MW billing commencement. Promised by 2026-06-01.
2026-03-25 - stated
2026-03-25 - delayed
Nscale colocation services contract for NC-1 865.0 USD. Promised by 2026-06-01.
2026-03-25 - stated
Duke Energy NC-1 capacity commitment 99.0 MW. Promised by 2029-05-16.
2026-03-25 - stated
2026-03-25 - stated
2026-03-25 - delayed
Duke Energy 24 MW service target for NC-1 24.0 MW. Promised by 2025-09-01.
2026-03-25 - stated
Duke Energy Capacity Agreement for NC-1 99.0 MW. Promised by 2029-05-16.
2026-03-25 - delayed
Nscale colocation contract 865000000.0 USD. Promised by 2026-06-30.
2026-03-25 - stated
2026-03-25 - stated
2026-05-26 - stated
2026-05-26 - stated
2026-05-26 - stated
2026-05-26 - stated
2026-05-26 - stated
2026-08-12 - stated
2026-08-13 - not yet verifiable
NC-1 40 MW run-rate billing 40.0 MW. Promised by 2026-08-31.
2026-08-13 - stated
2026-08-13 - stated
2026-08-13 - stated
2026-08-14 - not yet verifiable
NC-1 facility full billing target. Promised by 2026-08-31.
2026-08-14 - not yet verifiable
NC1 full run-rate billing 40.0 MW. Promised by 2026-08-31.
2026-08-14 - stated
2026-08-14 - not yet verifiable
NC1 contracted load billing by end of August 2026 40.0 MW. Promised by 2026-08-31.
2026-08-14 - stated
2026-08-21 - not yet verifiable