NC-1
Project of WhiteFiber
Capacity
What has actually been delivered, against what has been promised. Each figure links to the statement it came from.
| Stage | Capacity | As of | Source |
|---|---|---|---|
| Energized power flowing today | 40 MW | 2026-08-12 | NC-1 site active deployment |
| Contracted a customer is on the hook | 99 MW | 2025-08-07 | Duke Energy capacity agreement for NC-1 |
| Under construction | 40 MW | 2026-05-26 | NC-1 Phase I Data Center Capacity |
| Permitted | -- | ||
| Interconnect approved utility has agreed to deliver | -- | ||
| Interconnect requested in a queue, nothing approved | -- | ||
| Announced a press-release figure | 300 MW | 2026-08-21 | NC-1 potential to scale to 300 gross megawatts |
Who has claimed this site
Capacity commitments in the order they were announced. A commitment that ended shows why.
2025-12-17
Nscale - tenant ยท 10-year term source
Claims about this project
2025-07-10 - delayed
2025-07-10 - delayed
2025-07-10 - stated
2025-07-10 - delayed
2025-07-10 - delayed
NC-1 revenue start. Promised by 2026-05-01.
2025-07-22 - delayed
2025-07-22 - delayed
NC-1 revenue start. Promised by 2026-05-01.
2025-07-22 - stated
NC-1 initial capacity 24.0 MW.
2025-07-22 - delayed
2025-07-22 - stated
NC-1 phased expansion 40.0 MW.
2025-07-22 - stated
2025-07-28 - delayed
2025-07-28 - delayed
NC-1 revenue generation start date. Promised by 2026-05-31.
2025-07-28 - delayed
2025-07-28 - delayed
2025-07-28 - stated
2025-07-28 - delayed
2025-07-28 - delayed
2025-07-31 - stated
2025-07-31 - delayed
2025-07-31 - delayed
2025-07-31 - delayed
2025-08-07 - delayed
2025-08-07 - stated
NC-1 potential maximum capacity 200.0 MW.
2025-08-07 - stated
2025-08-07 - delayed
NC-1 revenue generation start. Promised by 2026-05-31.
2025-12-17 - stated
2025-12-17 - delayed
2025-12-17 - delayed
2025-12-17 - stated
2025-12-17 - stated
Contracted revenue from Nscale Services agreement 865000000.0 USD.
2025-12-17 - stated
2026-03-25 - delayed
2026-03-25 - stated
2026-03-25 - stated
Nscale Services Agreement at NC-1 865.0 USD.
2026-03-25 - delayed
Nscale 40 MW billing commencement. Promised by 2026-06-01.
2026-03-25 - stated
2026-03-25 - stated
NC-1 contingent purchase price increases based on Duke Energy capacity 8.0 USD. Promised by 2027-05-20.
2026-03-25 - delayed
2026-03-25 - stated
2026-03-25 - stated
2026-03-25 - stated
NC-1 conditional purchase price increase (2-year Duke Energy milestone) 8.0 USD. Promised by 2027-05-20.
2026-03-25 - delayed
2026-03-25 - stated
2026-03-25 - delayed
2026-03-25 - stated
NC-1 conditional purchase price increase (2-3 year Duke Energy milestone) 5.0 USD. Promised by 2028-05-20.
2026-03-25 - stated
NC-1 conditional purchase price increase (per-MW over 99 MW threshold) 5.0 USD. Promised by 2029-05-20.
2026-05-26 - stated
NC-1 Phase I Data Center Capacity 40.0 MW.
2026-05-26 - stated
2026-05-26 - stated
Bridge Facility Principal Amount 100.0 USD.
2026-05-26 - stated
B. Riley Securities Loan Assignment 20.0 USD.
2026-05-26 - stated
Original Issue Discount 3.0 percent.
2026-05-26 - stated
2026-05-26 - stated
NC-1 Phase I Minimum Leasing Target 80.0 percent.
2026-08-12 - stated
NC-1 site active deployment 40.0 MW.
2026-08-13 - not yet verifiable
2026-08-13 - stated
2026-08-13 - stated
Campus expansion toward 300 MW capacity 200.0 MW.
2026-08-13 - stated
Duke Energy NC-1 capacity expansion 45.0 MW.
2026-08-13 - stated
NC-1 10-year customer contract 865.0 USD.
2026-08-13 - stated
2026-08-14 - not yet verifiable
NC-1 facility full billing target. Promised by 2026-08-31.
2026-08-14 - not yet verifiable
2026-08-14 - stated
NC1 10-year contract 865.0 USD.
2026-08-14 - not yet verifiable
2026-08-14 - stated
2026-08-21 - stated
2026-08-21 - stated
2026-08-21 - stated
2026-08-21 - not yet verifiable
Full contracted run-rate billing expected by end of August. Promised by 2026-08-31.
2026-08-21 - stated