NC-1
Project of WhiteFiber
Where it stands
NC-1 in Madison, NC moved from construction into active customer deployment in August 2026, with about 20 MW of IT capacity available to Nscale and initial billing under way; management expected the full 40 MW Phase 1 to reach run-rate billing by end of August, but no passage confirms that was achieved. Later passages (through 2026-09-30) say only that NC-1 has begun billing, with 99 MW under utility agreement and a possible path to ~300 gross MW; project-level financing was in definitive documentation as of September. NC-2 and NC-3 are separate sites about 55 miles away and are not counted here.
20 MW in service · 20 MW under construction · 99 MW planned
| Phase | MW | Status | Date | Source |
|---|---|---|---|---|
| Phase 1 (initial tranche, Nscale) | 20 | ready for service | 2026-08-12 | Samir Tabar, chief executive officer, said about 20 megawatts of IT capacity at NC-1 was available for customer installation and testing. 2026-08-13 View cached copy (2026-08-31)Live source ↗ |
| Phase 1 (ramp to full 40 MW IT, Nscale) | 40 | under construction | Initial billing had started, with the full 40 megawatts expected to reach run-rate billing by the end of August. 2026-08-13 View cached copy (2026-08-31)Live source ↗ | |
| Next tranche (gross, awaiting Duke Energy schedule) | 45 | planned | Tabar also said Duke Energy is expected to provide a schedule for another 45 megawatts of gross NC-1 capacity. 2026-08-13 View cached copy (2026-08-31)Live source ↗ | |
| Longer-term expansion (gross) | 200 | planned | A longer-term 200-megawatt opportunity could take the campus toward 300 gross megawatts. 2026-08-13 View cached copy (2026-08-31)Live source ↗ |
Assessed October 18, 2026 from the newest filings, releases and reporting that name this project (newest relied on: September 30, 2026).
Capacity
What has actually been delivered, against what has been promised. Each figure links to the statement it came from.
| Stage | Capacity | As of | Source |
|---|---|---|---|
| Energized power flowing today | 40 MW | 2026-08-12 | NC-1 site active deployment |
| Contracted a customer is on the hook | 99 MW | 2026-06-09 | NC-1 power capacity milestone |
| Under construction | 40 MW | 2026-05-26 | NC-1 Phase I Data Center Capacity |
| Permitted | -- | ||
| Interconnect approved utility has agreed to deliver | 99 MW | 2026-09-13 | Duke Energy NC-1 power supply commitment |
| Interconnect requested in a queue, nothing approved | -- | ||
| Announced a press-release figure | 300 MW | 2026-08-21 | NC-1 capacity potential |
Who has claimed this site
Capacity commitments in the order they were announced. A commitment that ended shows why.
Claims about this project
Site intelligence
How we located this site
- Starting point (the project's stated locality) 2026-10-19
805 Island Drive, Madison, NC → 36.40111, -79.98713 (street) - Located from a published address 2026-10-19
805 Island Drive, Madison, NC → 36.40111, -79.98713 (street) - Located from a published address 2026-10-19
805 Island Drive, Madison, North Carolina → 36.40111, -79.98713 (street), 0.0 km from seed - OpenStreetMap features nearby 2026-10-19
0 named match(es)
- 2023-05-10 vs 2023-03-30: vegetation recovery visible
- 2023-10-10 vs 2023-09-30: vegetation recovery visible
- 2024-04-22 vs 2024-04-07: vegetation recovery visible
- 2023-11-02 vs 2023-09-15: clearing or grading visible
- 2024-04-18 vs 2024-03-24: vegetation recovery visible
Satellite imagery on this page is drawn from the Google Earth satellite basemap, USDA NAIP aerial photography (~1 m/pixel), ESA Sentinel-2 multispectral (10 m, with per-date cloud masks), NASA / USGS Landsat 8/9 (30 m, plus surface temperature), ESA Sentinel-1 radar (all-weather, night), NASA ECOSTRESS thermal (~70 m), and NASA Black Marble night lights (500 m, daily). Each image is dated, labelled by source and pixel resolution, and downloadable at its native size; cloudy dates are kept and marked rather than hidden. New scenes are pulled daily as each provider publishes them.