NC-1

Project of WhiteFiber

Kind
datacenter
Location
805 Island Drive, Madison, NC
County
Rockingham
State/region
NC
Country
US
Status
partially operational as of September 30, 2026

Where it stands

NC-1 in Madison, NC moved from construction into active customer deployment in August 2026, with about 20 MW of IT capacity available to Nscale and initial billing under way; management expected the full 40 MW Phase 1 to reach run-rate billing by end of August, but no passage confirms that was achieved. Later passages (through 2026-09-30) say only that NC-1 has begun billing, with 99 MW under utility agreement and a possible path to ~300 gross MW; project-level financing was in definitive documentation as of September. NC-2 and NC-3 are separate sites about 55 miles away and are not counted here.

20 MW in service · 20 MW under construction · 99 MW planned

PhaseMWStatusDateSource
Phase 1 (initial tranche, Nscale)20ready for service2026-08-12Samir Tabar, chief executive officer, said about 20 megawatts of IT capacity at NC-1 was available for customer installation and testing.
2026-08-13 View cached copy (2026-08-31)Live source ↗
Phase 1 (ramp to full 40 MW IT, Nscale)40under constructionInitial billing had started, with the full 40 megawatts expected to reach run-rate billing by the end of August.
2026-08-13 View cached copy (2026-08-31)Live source ↗
Next tranche (gross, awaiting Duke Energy schedule)45plannedTabar also said Duke Energy is expected to provide a schedule for another 45 megawatts of gross NC-1 capacity.
2026-08-13 View cached copy (2026-08-31)Live source ↗
Longer-term expansion (gross)200plannedA longer-term 200-megawatt opportunity could take the campus toward 300 gross megawatts.
2026-08-13 View cached copy (2026-08-31)Live source ↗

Assessed October 18, 2026 from the newest filings, releases and reporting that name this project (newest relied on: September 30, 2026).

Capacity

What has actually been delivered, against what has been promised. Each figure links to the statement it came from.

StageCapacityAs ofSource
Energized power flowing today40 MW2026-08-12NC-1 site active deployment
Contracted a customer is on the hook99 MW2026-06-09NC-1 power capacity milestone
Under construction40 MW2026-05-26NC-1 Phase I Data Center Capacity
Permitted--
Interconnect approved utility has agreed to deliver99 MW2026-09-13Duke Energy NC-1 power supply commitment
Interconnect requested in a queue, nothing approved--
Announced a press-release figure300 MW2026-08-21NC-1 capacity potential

Who has claimed this site

Capacity commitments in the order they were announced. A commitment that ended shows why.

2025-12-17
Nscale Services US Inc. - anchor tenant · 40 MW · 10-year term source

Claims about this project

2025-07-10 - verified
Duke Energy 24 MW capacity commitment 24.0 MW. Promised by 2025-09-01.
2025-07-10 - verified
NC-1 revenue start. Promised by 2026-05-01.
2025-07-10 - verified
NC-1 initial 24 MW completion 24.0 MW. Promised by 2026-03-31.
2025-07-10 - verified
Duke Energy 40 MW capacity commitment 40.0 MW. Promised by 2026-04-01.
2025-07-10 - stated
Duke Energy 99 MW capacity commitment 99.0 MW. Promised by 2029-05-16.
2025-07-22 - stated
2025-07-22 - verified
Duke Energy - 40 MW 40.0 MW. Promised by 2026-04-01.
2025-07-22 - verified
NC-1 revenue start. Promised by 2026-05-01.
2025-07-22 - stated
Duke Energy - 99 MW 99.0 MW. Promised by 2029-05-16.
2025-07-22 - stated
2025-07-22 - verified
Duke Energy - 24 MW 24.0 MW. Promised by 2025-09-01.
2025-07-28 - verified
NC-1 24 MW energization in Q1 2026 24.0 MW. Promised by 2026-03-31.
2025-07-28 - verified
NC-1 40 MW cumulative capacity by Q2 2026 40.0 MW. Promised by 2026-06-30.
2025-07-28 - verified
Duke Energy capacity agreement - Phase 1 24.0 MW. Promised by 2025-09-01.
2025-07-28 - verified
NC-1 revenue generation start date. Promised by 2026-05-31.
2025-07-28 - verified
NC-1 initial capacity completion 24.0 MW. Promised by 2026-03-31.
2025-07-28 - verified
Duke Energy capacity agreement - Phase 2 40.0 MW. Promised by 2026-04-01.
2025-07-28 - stated
Duke Energy capacity agreement - Phase 3 99.0 MW. Promised by 2029-05-16.
2025-07-31 - verified
Duke Energy capacity commitment - 40 MW milestone 40.0 MW. Promised by 2026-04-01.
2025-07-31 - verified
NC-1 initial capacity operational date 24.0 MW. Promised by 2026-03-31.
2025-07-31 - verified
Duke Energy capacity commitment - 24 MW milestone 24.0 MW. Promised by 2025-09-01.
2025-07-31 - stated
Duke Energy capacity commitment - 99 MW milestone 99.0 MW. Promised by 2029-05-16.
2025-08-07 - verified
NC-1 initial capacity completion 24.0 MW. Promised by 2026-03-31.
2025-08-07 - stated
Duke Energy capacity agreement for NC-1 99.0 MW. Promised by 2029-05-16.
2025-08-07 - verified
NC-1 revenue generation start. Promised by 2026-05-31.
2025-08-07 - stated
2025-08-27 - verified
NC-1 40 MW Duke power by Apr 2026 40.0 MW. Promised by 2026-04-30.
2025-08-27 - verified
NC-1 24 MW Duke power by Sep 2025 24.0 MW. Promised by 2025-09-30.
2025-08-27 - verified
NC-1 COD Q1 2026. Promised by 2026-03-31.
2025-08-27 - stated
2025-08-27 - stated
2025-08-27 - stated
2025-12-17 - delayed
Billing commencement for second 20 MW phase 20.0 MW. Promised by 2026-05-30.
2025-12-17 - delayed
NC-1 second 20 MW ready-for-service 20.0 MW. Promised by 2026-05-30.
2025-12-17 - stated
2025-12-17 - stated
2025-12-17 - stated
2025-12-17 - stated
2025-12-17 - verified
NC-1 first 20 MW ready-for-service 20.0 MW. Promised by 2026-04-30.
2025-12-17 - verified
Billing commencement for first 20 MW phase 20.0 MW. Promised by 2026-04-30.
2026-01-25 - stated
NC-1 99 MW total capacity target 99.0 MW. Promised by 2030-01-25.
2026-01-25 - stated
2026-01-25 - verified
Duke Energy 44 MW power by April 2026 44.0 MW. Promised by 2026-04-30.
2026-01-25 - delayed
NC-1 project-level financing. Promised by 2026-03-31.
2026-01-25 - outcome unconfirmed
NC-1 Phase 1 capacity in April and May 2026 40.0 MW. Promised by 2026-05-31.
2026-01-26 - delayed
2026-03-25 - verified
Duke Energy 24 MW service target for NC-1 24.0 MW. Promised by 2025-09-01.
2026-03-25 - stated
Duke Energy NC-1 capacity commitment 99.0 MW. Promised by 2029-05-16.
2026-03-25 - stated
2026-03-25 - verified
Nscale colocation contract 865000000.0 USD. Promised by 2026-06-30.
2026-03-25 - stated
2026-03-25 - stated
Duke Energy 99 MW service target for NC-1 99.0 MW. Promised by 2029-05-16.
2026-03-25 - verified
Duke Energy 40 MW service target for NC-1 40.0 MW. Promised by 2026-04-01.
2026-03-25 - stated
2026-03-25 - verified
Nscale 40 MW billing commencement. Promised by 2026-06-01.
2026-03-25 - stated
2026-03-25 - stated
2026-03-25 - stated
2026-03-25 - verified
Nscale colocation services contract for NC-1 865.0 USD. Promised by 2026-06-01.
2026-05-26 - stated
2026-05-26 - stated
2026-05-26 - stated
2026-05-26 - stated
2026-05-26 - stated
2026-06-09 - outcome unconfirmed
NC-1 full revenue contribution. Promised by 2026-09-30.
2026-06-09 - stated
NC-1 power capacity milestone 99.0 MW. Promised by 2029-05-31.
2026-06-09 - verified
NC-1 billing commencement. Promised by 2026-06-30.
2026-08-12 - outcome unconfirmed
NC-1 full contracted run-rate billing 40.0 MW. Promised by 2026-08-31.
2026-08-12 - stated
2026-08-12 - stated
2026-08-13 - outcome unconfirmed
NC-1 40 MW run-rate billing 40.0 MW. Promised by 2026-08-31.
2026-08-13 - stated
2026-08-13 - stated
2026-08-13 - stated
2026-08-13 - outcome unconfirmed
2026-08-14 - outcome unconfirmed
NC-1 facility full billing target. Promised by 2026-08-31.
2026-08-14 - stated
2026-08-14 - stated
2026-08-14 - stated
2026-08-14 - stated
2026-08-14 - outcome unconfirmed
NC1 data center billing capacity 40.0 MW. Promised by 2026-08-31.
2026-08-14 - outcome unconfirmed
NC1 full run-rate billing 40.0 MW. Promised by 2026-08-31.
2026-08-14 - stated
2026-08-14 - outcome unconfirmed
NC-1 facility full billing deployment. Promised by 2026-08-31.
2026-08-14 - outcome unconfirmed
NC1 contracted load billing by end of August 2026 40.0 MW. Promised by 2026-08-31.
2026-08-17 - stated
2026-08-21 - outcome unconfirmed
2026-08-21 - stated
2026-08-21 - stated
2026-08-21 - outcome unconfirmed
NC-1 full billing milestone 40.0 MW. Promised by 2026-08-31.
2026-09-10 - stated
2026-09-10 - stated
2026-09-13 - stated
2026-09-13 - stated
2026-09-13 - stated
Duke Energy NC-1 power supply commitment 99.0 MW. Promised by 2029-05-31.
2026-09-14 - stated
2026-09-14 - stated
2026-09-14 - stated
2026-09-14 - stated
2026-09-30 - outcome unconfirmed
NC-1 full 40 MW run-rate billing by end of August 40.0 MW. Promised by 2026-08-31.
2026-09-30 - stated
2026-09-30 - stated
2026-09-30 - stated

Site intelligence

Analytical estimate. Each site below is located from public records (filings, releases, news, OpenStreetMap) and checked against free satellite imagery; "How we located this site" lists every step and the score it earned. The conclusion is computed from night-time lights, surface heat and year-over-year change, with the dates it rests on. These are hypotheses under active tracking, not legal parcels or an official endorsement.
805 ISLAND DR, MADISON, NC, 27025
Probable
Rockingham, NC
36.4011, -79.9871
Approximate address 750 Island Dr, Madison, NC 27025, USA Reverse-geocoded from the candidate centroid; not a permit-confirmed parcel address.
Conclusion so far Under construction: the site is changing year over year. · confidence 60%
In progress: night-time lights at the site ran 1.58x the surrounding area (0 of 13 clear nights, 2026-06-24 to 2026-09-17); surface temperature +0.4 K against its surroundings (17 pass(es), 2026-07-05 to 2026-10-16); vegetation -0.10 NDVI against the same season a year earlier. Based on 53 clear observation(s) from 2026-06-21 to 2026-10-19.
What would change this: Change stopping for a season, or lights/heat showing the site has started operating.
Latest clear imagery: ECOSTRESS thermal 2026-10-16 · Sentinel-2 2026-10-14 · Landsat 2026-10-08 · radar 2026-10-02 · Google 2026-09-29 · night lights 2026-09-17 · NAIP 2022-06-04
Newest clear images188 clear image date(s)
Thermal view of whitefiber-nc-1, 2026-10-16 (ECOSTRESS thermal)
2026-10-16ECOSTRESS thermal · 70 m/pixel
Visual view of whitefiber-nc-1, 2026-10-14 (Sentinel-2)
2026-10-14Sentinel-2 · 10 m/pixel
Thermal view of whitefiber-nc-1, 2026-10-12 (ECOSTRESS thermal)
2026-10-12ECOSTRESS thermal · 70 m/pixel
Visual view of whitefiber-nc-1, 2026-10-08 (Landsat 8/9)
2026-10-08Landsat 8/9 · 30 m/pixel
How we located this site
45/100 (probable): street location 25 + 2 independent source families 20
  1. Starting point (the project's stated locality) 2026-10-19
    805 Island Drive, Madison, NC → 36.40111, -79.98713 (street)
  2. Located from a published address 2026-10-19
    805 Island Drive, Madison, NC → 36.40111, -79.98713 (street)
  3. Located from a published address 2026-10-19
    805 Island Drive, Madison, North Carolina → 36.40111, -79.98713 (street), 0.0 km from seed
  4. OpenStreetMap features nearby 2026-10-19
    0 named match(es)
Recent changes
  • 2023-05-10 vs 2023-03-30: vegetation recovery visible
  • 2023-10-10 vs 2023-09-30: vegetation recovery visible
  • 2024-04-22 vs 2024-04-07: vegetation recovery visible
  • 2023-11-02 vs 2023-09-15: clearing or grading visible
  • 2024-04-18 vs 2024-03-24: vegetation recovery visible

Satellite imagery on this page is drawn from the Google Earth satellite basemap, USDA NAIP aerial photography (~1 m/pixel), ESA Sentinel-2 multispectral (10 m, with per-date cloud masks), NASA / USGS Landsat 8/9 (30 m, plus surface temperature), ESA Sentinel-1 radar (all-weather, night), NASA ECOSTRESS thermal (~70 m), and NASA Black Marble night lights (500 m, daily). Each image is dated, labelled by source and pixel resolution, and downloadable at its native size; cloudy dates are kept and marked rather than hidden. New scenes are pulled daily as each provider publishes them.