jain.com

Billing commencement for second 20 MW phase

Company: WhiteFiber - Project: NC-1

This claim was marked delayed on October 10, 2026. Recorded automatically from the cited source when it was published, then queued for evidence review.

How this was decided: Automated extraction from the cited source. The claim is preserved below exactly as it was originally published, so the record shows what was asserted as well as what became of it.

Subject kind
facility timeline
Statement date
2025-12-17
Promised by
2026-05-30
Promised amount
20.0 MW
Current status
delayed

What the later record shows

The date slipped · new target August 31, 2026

The remaining 20 MW was not billing by May 30, 2026; the August 2026 10-Q pushed Nscale delivery to Q3. The CEO later targeted full 40 MW run-rate billing for the end of August, but completion is not confirmed.

“Management expects to begin delivering capacity to Nscale during the third quarter and for NC-1 to start generating revenues 30 days after completion.”
2026-08-11 · WhiteFiber 10-Q filed 2026-08-12 View cached copy (2026-08-31)Live source ↗
“Initial billing has commenced, and we expect to reach full contracted run-rate billing across the 40 megawatts of contracted IT load later this month”
2026-08-21 · WYFI Stock Rallies On Earnings Beat, CEO Says NC-1 Has Entered ‘Active Customer Deployment’ With Initial Billing Underwa View cached copy (2026-08-31)Live source ↗

Checked October 10, 2026 against filings, releases and reporting published after the claim was made. Quotes are verbatim from the linked documents.

The claim, verbatim

Billing for the remaining 20 MW is anticipated to commence on May 30, 2026

Source (primary)

WhiteFiber 8-K filed 2025-12-18 (SEC EDGAR, sec_filing)
View cached copy (2026-08-31)Live source ↗

Quote: “the remaining 20 MW anticipated to commence on May 30, 2026”

How we checked this

Checked on October 11, 2026. The cited source supports every part of this claim.

The filing's billing sentence states that the remaining 20 MW is anticipated to commence on May 30, 2026, so this refers to the start of billing.

Confirmed in the source:

What we did: Read our cached copy of SEC EDGAR (https://www.sec.gov/Archives/edgar/data/2042022/000121390025123321/ea0269918-8k_white.htm) in full (7,155 characters, retrieved August 31, 2026) and checked each assertion in the claim against it.

Additional evidence

confirms WhiteFiber 8-K filed 2025-12-18

Quote: “the remaining 20 MW anticipated to commence on May 30, 2026”

View cached copy (2026-08-31)Live source ↗

delays WhiteFiber 10-Q filed 2026-08-12

Quote: “Management expects to begin delivering capacity to Nscale during the third quarter and for NC-1 to start generating revenues 30 days after completion.”

View cached copy (2026-08-31)Live source ↗

delays WYFI Stock Rallies On Earnings Beat, CEO Says NC-1 Has Entered ‘Active Customer Deployment’ With Initial Billing Underway - Stocktwits

Quote: “Initial billing has commenced, and we expect to reach full contracted run-rate billing across the 40 megawatts of contracted IT load later this month”

View cached copy (2026-08-31)Live source ↗

Record of changes

September 2, 2026 — stated
Automated extraction from the cited source. Recorded automatically from the cited source when it was published, then queued for evidence review.
September 3, 2026 — delayed
Automated extraction from the cited source. Recorded automatically from the cited source when it was published, then queued for evidence review.
October 9, 2026 — outcome unconfirmed
Automated extraction from the cited source. Recorded automatically from the cited source when it was published, then queued for evidence review.
October 10, 2026 — delayed
Automated extraction from the cited source. Recorded automatically from the cited source when it was published, then queued for evidence review.