$100M delayed-draw tranche conditional on Phase 1 completion

Company: WhiteFiber

Subject kind
financing
Statement date
2026-11-10
Promised amount
100000000.0 USD
Current status
stated

The claim, verbatim

The $100 million delayed-draw tranche requires final completion of the 40 MW first phase of NC-1 and pro forma financial tests.

Source (primary)

WhiteFiber lines up a $300 million Morgan Stanley loan for its North Carolina AI data center - MLQ.ai (-, news_article)
View cached copy (2026-11-11)Live source ↗Archive.org ↗

Quote: “The delayed draw requires final completion of the 40 MW first phase and pro forma financial tests”

How we checked this

This claim has not yet been checked assertion-by-assertion against its source. It carries a cited source and quote, but the deeper check has not run. When it does, the result appears here whatever it says.

Additional evidence

confirms WhiteFiber lines up a $300 million Morgan Stanley loan for its North Carolina AI data center - MLQ.ai

Quote: “The delayed draw requires final completion of the 40 MW first phase and pro forma financial tests”

View cached copy (2026-11-11)Live source ↗Archive.org ↗