NC-1 35 MW of 40 MW operational
Company: WhiteFiber
The claim, verbatim
Approximately 35 MW of NC-1's contracted 40 MW IT deployment is operational, with work ongoing to bring the remaining 5 MW online.
Source (primary)
Two North Carolina warehouse sites are now WhiteFiber's, with plans to turn 500,000 square feet into data centers. - Stock Titan (-, news_article)
View cached copy (2026-11-06)Live source ↗Archive.org ↗
Quote: “Approximately 35 MW of the contracted 40 MW IT deployment is now operational, with work ongoing to bring the remaining 5 MW online.”
How we checked this
This claim has not yet been checked assertion-by-assertion against its source. It carries a cited source and quote, but the deeper check has not run. When it does, the result appears here whatever it says.
Additional evidence
confirms Two North Carolina warehouse sites are now WhiteFiber's, with plans to turn 500,000 square feet into data centers. - Stock Titan
Quote: “Approximately 35 MW of the contracted 40 MW IT deployment is now operational, with work ongoing to bring the remaining 5 MW online.”