jain.com

NC-1 contracted 40 MW IT deployment status

Company: WhiteFiber

Subject kind
facility capacity
Statement date
2026-11-03
Promised amount
40.0 MW
Current status
stated

The claim, verbatim

Approximately 35 MW of NC-1's contracted 40 MW IT deployment is operational, with work continuing on the remaining 5 MW.

Source (primary)

WhiteFiber Buys Two North Carolina Data Center Sites for $60 Million - Securities.io (-, news_article)
View cached copy (2026-11-04)Live source ↗Archive.org ↗

Quote: “Approximately 35 megawatts of the contracted 40-megawatt IT deployment are now operational, with work continuing on the remaining 5 megawatts”

How we checked this

This claim has not yet been checked assertion-by-assertion against its source. It carries a cited source and quote, but the deeper check has not run. When it does, the result appears here whatever it says.

Additional evidence

confirms WhiteFiber Buys Two North Carolina Data Center Sites for $60 Million - Securities.io

Quote: “Approximately 35 megawatts of the contracted 40-megawatt IT deployment are now operational, with work continuing on the remaining 5 megawatts”

View cached copy (2026-11-04)Live source ↗Archive.org ↗