jain.com

NC-1 project-level financing

Company: WhiteFiber - Project: NC-1

This claim was marked delayed on October 10, 2026. Recorded automatically from the cited source when it was published, then queued for evidence review.

How this was decided: Automated extraction from the cited source. The claim is preserved below exactly as it was originally published, so the record shows what was asserted as well as what became of it.

Subject kind
financing
Statement date
2026-01-25
Promised by
2026-03-31
Current status
delayed

What the later record shows

The date slipped

As of August 2026, the NC-1 project financing was still only a proposal under exclusivity with lenders, and its closing was still 'anticipated'. It did not close in Q1 2026, and no new date was given.

“The Company has entered into exclusivity with a consortium of lenders in connection with a proposed secured financing for its NC-1 project.”
2026-08-11 · WhiteFiber 10-Q filed 2026-08-12 View cached copy (2026-08-31)Live source ↗
“Together with the anticipated closing of our proposed project-level financing for NC-1, which remains subject to the completion of definitive documentation and satisfaction of customary approvals and closing conditions”
2026-08-20 · whitefiber 8-K exhibit (ea030292501ex99-3.htm) View cached copy (2026-08-30)Live source ↗

Checked October 10, 2026 against filings, releases and reporting published after the claim was made. Quotes are verbatim from the linked documents.

The claim, verbatim

Project-level financing for NC-1 is expected in Q1 2026

Source (primary)

whitefiber 8-K exhibit (ea027401701ex99-1_white.htm) (SEC EDGAR (8-K Ex), press_release)
View cached copy (2026-09-21)Live source ↗

Quote: “Project - level financing expected for 1Q 2026”

How we checked this

Checked on October 11, 2026. The cited source supports every part of this claim.

The NC-1 Nscale anchor contract slide lists project-level financing as expected for 1Q 2026.

Confirmed in the source:

What we did: Read our cached copy of SEC EDGAR (8-K Ex) (https://www.sec.gov/Archives/edgar/data/2042022/000121390026007474/ea027401701ex99-1_white.htm) in full (23,241 characters, retrieved September 21, 2026) and checked each assertion in the claim against it.

Additional evidence

confirms whitefiber 8-K exhibit (ea027401701ex99-1_white.htm)

Quote: “Project - level financing expected for 1Q 2026”

View cached copy (2026-09-21)Live source ↗

delays whitefiber 8-K exhibit (ea030292501ex99-3.htm)

Quote: “Together with the anticipated closing of our proposed project-level financing for NC-1, which remains subject to the completion of definitive documentation and satisfaction of customary approvals and closing conditions”

View cached copy (2026-08-30)Live source ↗

delays WhiteFiber 10-Q filed 2026-08-12

Quote: “The Company has entered into exclusivity with a consortium of lenders in connection with a proposed secured financing for its NC-1 project.”

View cached copy (2026-08-31)Live source ↗

Record of changes

September 21, 2026 — stated
Automated extraction from the cited source. Recorded automatically from the cited source when it was published, then queued for evidence review.
September 22, 2026 — delayed
Automated extraction from the cited source. Recorded automatically from the cited source when it was published, then queued for evidence review.
October 9, 2026 — outcome unconfirmed
Automated extraction from the cited source. Recorded automatically from the cited source when it was published, then queued for evidence review.
October 10, 2026 — delayed
Automated extraction from the cited source. Recorded automatically from the cited source when it was published, then queued for evidence review.