Duke Energy capacity commitment - 40 MW milestone

Company: WhiteFiber - Project: NC-1

Subject kind
partnership
Statement date
2025-07-31
Promised by
2026-04-01
Promised amount
40.0 MW
Current status
verified

What the later record shows

Delivered; the record does not say when

The June 2026 deck reports Duke completed work for the initial 54 gross MW, covering the 40 MW milestone. When that happened is not stated.

“Duke Energy has completed the work required to deliver the initial 54 gross MW of utility power to the NC-1 site.”
2026-06-09 · whitefiber 8-K exhibit (ea029430601ex99-1.htm) View cached copy (2026-09-06)Live source ↗

Checked October 10, 2026 against filings, releases and reporting published after the claim was made. Quotes are verbatim from the linked documents.

The claim, verbatim

Duke Energy agreed to provide 40 MW gross service to NC-1 property by April 1, 2026

Source (primary)

WhiteFiber S-1/A filed 2025-08-01 (SEC EDGAR, sec_filing)
View cached copy (2026-08-31)Live source ↗

Quote: “Duke Energy agreed to use commercially reasonable efforts to achieve 40 MW (gross) of service to the Property by April 1, 2026”

How we checked this

Checked on October 11, 2026. The cited source supports part of this claim, but not all of it.

The prospectus describes Duke Energy's undertaking as a commercially reasonable efforts obligation, not a firm agreement to provide 40 MW by April 1, 2026, so the claim overstates the commitment.

Confirmed in the source:

We could not confirm this from the cited source:

That does not mean it is false — only that this source does not establish it, as of the date above. If we find a source that settles it, we will re-check and update this page.

What we did: Read our cached copy of SEC EDGAR (https://www.sec.gov/Archives/edgar/data/2042022/000121390025070709/ea0249945-04.htm) in full (845,158 characters, retrieved August 31, 2026) and checked each assertion in the claim against it.

Additional evidence

confirms WhiteFiber S-1/A filed 2025-08-01

Quote: “Duke Energy agreed to use commercially reasonable efforts to achieve 40 MW (gross) of service to the Property by April 1, 2026”

View cached copy (2026-08-31)Live source ↗

confirms whitefiber 8-K exhibit (ea029430601ex99-1.htm)

Quote: “Duke Energy has completed the work required to deliver the initial 54 gross MW of utility power to the NC-1 site.”

View cached copy (2026-09-06)Live source ↗

Record of changes

September 2, 2026 — stated
Automated extraction from the cited source. Recorded automatically from the cited source when it was published, then queued for evidence review.
September 3, 2026 — delayed
Automated extraction from the cited source. Recorded automatically from the cited source when it was published, then queued for evidence review.
October 9, 2026 — outcome unconfirmed
Automated extraction from the cited source. Recorded automatically from the cited source when it was published, then queued for evidence review.
October 10, 2026 — verified
Automated extraction from the cited source. Recorded automatically from the cited source when it was published, then queued for evidence review.