NC-1 first 40 MW readiness and customer acceptance

Company: WhiteFiber

Subject kind
facility capacity
Statement date
2026-11-10
Promised amount
40.0 MW
Current status
stated

The claim, verbatim

Initial funding is conditioned on readiness and customer acceptance of the first 40 megawatts of capacity at the NC-1 data center in Madison, North Carolina.

Source (primary)

No loans funded as of Nov. 9 under WhiteFiber (WYFI) subsidiaries’ data center financing deal. - Stock Titan (-, news_article)
View cached copy (2026-11-11)Live source ↗

Quote: “Initial funding is subject to satisfaction or waiver of conditions relating to readiness and customer acceptance of the first 40 megawatts of capacity at the Borrower's NC-1 data center”

How we checked this

This claim has not yet been checked assertion-by-assertion against its source. It carries a cited source and quote, but the deeper check has not run. When it does, the result appears here whatever it says.

Additional evidence

confirms No loans funded as of Nov. 9 under WhiteFiber (WYFI) subsidiaries’ data center financing deal. - Stock Titan

Quote: “Initial funding is subject to satisfaction or waiver of conditions relating to readiness and customer acceptance of the first 40 megawatts of capacity at the Borrower's NC-1 data center”

View cached copy (2026-11-11)Live source ↗