Duke Energy 24 MW service target for NC-1
Company: WhiteFiber - Project: NC-1
What the later record shows
Delivered; the record does not say when
A June 2026 investor presentation says Duke Energy completed the work to deliver the initial 54 gross MW to NC-1, which covers the 24 MW. No passage says when it was completed relative to September 1, 2025.
“Duke Energy has completed the work required to deliver the initial 54 gross MW of utility power to the NC-1 site.”
2026-06-09 · whitefiber 8-K exhibit (ea029430601ex99-1.htm) View cached copy (2026-09-06)Live source ↗
Checked October 10, 2026 against filings, releases and reporting published after the claim was made. Quotes are verbatim from the linked documents.
The claim, verbatim
Duke Energy agreed to use commercially reasonable efforts to achieve 24 MW gross service to NC-1 by September 1, 2025
Source (primary)
WhiteFiber 10-K filed 2026-03-26 (SEC EDGAR, sec_filing)
View cached copy (2026-08-31)Live source ↗
Quote: “Duke Energy agreed to use commercially reasonable efforts to achieve 24 MW (gross) of service to NC-1 by September 1, 2025”
How we checked this
Checked on October 11, 2026. The cited source supports every part of this claim.
The 10-K describes a Capacity Agreement under which Duke Energy agreed to use commercially reasonable efforts to reach 24 MW (gross) at NC-1 by September 1, 2025.
Confirmed in the source:
- Duke Energy agreed to use commercially reasonable efforts on service to NC-1
- The target was 24 MW (gross) of service
- The target date was September 1, 2025
What we did: Read our cached copy of SEC EDGAR (https://www.sec.gov/Archives/edgar/data/2042022/000121390026034341/ea0278305-10k_white.htm) in full (600,249 characters, retrieved August 31, 2026) and checked each assertion in the claim against it.
Additional evidence
confirms WhiteFiber 10-K filed 2026-03-26
Quote: “Duke Energy agreed to use commercially reasonable efforts to achieve 24 MW (gross) of service to NC-1 by September 1, 2025”
confirms whitefiber 8-K exhibit (ea029430601ex99-1.htm)
Quote: “Duke Energy has completed the work required to deliver the initial 54 gross MW of utility power to the NC-1 site.”