Duke Energy 40 MW service target for NC-1

Company: WhiteFiber - Project: NC-1

Subject kind
partnership
Statement date
2026-03-25
Promised by
2026-04-01
Promised amount
40.0 MW
Current status
verified

What the later record shows

Delivered; the record does not say when

A June 2026 investor deck (data as of May 31, 2026) says Duke completed the work to deliver the initial 54 gross MW, which exceeds 40 MW. No passage says whether 40 MW was reached by April 1, 2026.

“Duke Energy has completed the work required to deliver the initial 54 gross MW of utility power to the NC-1 site.”
2026-06-09 · whitefiber 8-K exhibit (ea029430601ex99-1.htm) View cached copy (2026-09-06)Live source ↗

Checked October 10, 2026 against filings, releases and reporting published after the claim was made. Quotes are verbatim from the linked documents.

The claim, verbatim

Duke Energy agreed to use commercially reasonable efforts to achieve 40 MW gross service to NC-1 by April 1, 2026

Source (primary)

WhiteFiber 10-K filed 2026-03-26 (SEC EDGAR, sec_filing)
View cached copy (2026-08-31)Live source ↗

Quote: “40 MW (gross) by April 1, 2026”

How we checked this

Checked on October 11, 2026. The cited source supports every part of this claim.

The same Capacity Agreement passage in the 10-K sets a commercially-reasonable-efforts target of 40 MW (gross) at NC-1 by April 1, 2026.

Confirmed in the source:

What we did: Read our cached copy of SEC EDGAR (https://www.sec.gov/Archives/edgar/data/2042022/000121390026034341/ea0278305-10k_white.htm) in full (600,249 characters, retrieved August 31, 2026) and checked each assertion in the claim against it.

Additional evidence

confirms WhiteFiber 10-K filed 2026-03-26

Quote: “40 MW (gross) by April 1, 2026”

View cached copy (2026-08-31)Live source ↗

confirms whitefiber 8-K exhibit (ea029430601ex99-1.htm)

Quote: “Duke Energy has completed the work required to deliver the initial 54 gross MW of utility power to the NC-1 site.”

View cached copy (2026-09-06)Live source ↗

Record of changes

September 1, 2026 — stated
Automated extraction from the cited source. Recorded automatically from the cited source when it was published, then queued for evidence review.
September 2, 2026 — delayed
Automated extraction from the cited source. Recorded automatically from the cited source when it was published, then queued for evidence review.
October 9, 2026 — outcome unconfirmed
Automated extraction from the cited source. Recorded automatically from the cited source when it was published, then queued for evidence review.
October 10, 2026 — verified
Automated extraction from the cited source. Recorded automatically from the cited source when it was published, then queued for evidence review.