Duke Energy 40 MW service target for NC-1
Company: WhiteFiber - Project: NC-1
What the later record shows
Delivered; the record does not say when
A June 2026 investor deck (data as of May 31, 2026) says Duke completed the work to deliver the initial 54 gross MW, which exceeds 40 MW. No passage says whether 40 MW was reached by April 1, 2026.
“Duke Energy has completed the work required to deliver the initial 54 gross MW of utility power to the NC-1 site.”
2026-06-09 · whitefiber 8-K exhibit (ea029430601ex99-1.htm) View cached copy (2026-09-06)Live source ↗
Checked October 10, 2026 against filings, releases and reporting published after the claim was made. Quotes are verbatim from the linked documents.
The claim, verbatim
Duke Energy agreed to use commercially reasonable efforts to achieve 40 MW gross service to NC-1 by April 1, 2026
Source (primary)
WhiteFiber 10-K filed 2026-03-26 (SEC EDGAR, sec_filing)
View cached copy (2026-08-31)Live source ↗
Quote: “40 MW (gross) by April 1, 2026”
How we checked this
Checked on October 11, 2026. The cited source supports every part of this claim.
The same Capacity Agreement passage in the 10-K sets a commercially-reasonable-efforts target of 40 MW (gross) at NC-1 by April 1, 2026.
Confirmed in the source:
- Duke Energy agreed to use commercially reasonable efforts on service to NC-1
- The target was 40 MW (gross) of service
- The target date was April 1, 2026
What we did: Read our cached copy of SEC EDGAR (https://www.sec.gov/Archives/edgar/data/2042022/000121390026034341/ea0278305-10k_white.htm) in full (600,249 characters, retrieved August 31, 2026) and checked each assertion in the claim against it.
Additional evidence
confirms WhiteFiber 10-K filed 2026-03-26
Quote: “40 MW (gross) by April 1, 2026”
confirms whitefiber 8-K exhibit (ea029430601ex99-1.htm)
Quote: “Duke Energy has completed the work required to deliver the initial 54 gross MW of utility power to the NC-1 site.”