Duke Energy 44 MW power by April 2026
Company: WhiteFiber - Project: NC-1
What the later record shows
Delivered; the record does not say when
The June 2026 deck (data as of May 31, 2026) says Duke completed work for the initial 54 gross MW, which exceeds 44 MW. It does not say whether 44 MW was reached by April 2026; the 10-K's April-27/May-27 schedule hints it may have been later.
“we intend to complete the first 27 gross MW (gross) of service at NC-1 in April 2026, with another 27 gross MW (gross) of service in May 2026”
2026-03-25 · WhiteFiber 10-K filed 2026-03-26 View cached copy (2026-08-31)Live source ↗
“Duke Energy has completed the work required to deliver the initial 54 gross MW of utility power to the NC-1 site.”
2026-06-09 · whitefiber 8-K exhibit (ea029430601ex99-1.htm) View cached copy (2026-09-06)Live source ↗
Checked October 10, 2026 against filings, releases and reporting published after the claim was made. Quotes are verbatim from the linked documents.
The claim, verbatim
Duke Energy has agreed to commercially reasonable efforts to achieve 44 MW of power service by April 2026 for NC-1
Source (primary)
whitefiber 8-K exhibit (ea027401701ex99-1_white.htm) (SEC EDGAR (8-K Ex), press_release)
View cached copy (2026-09-21)Live source ↗
Quote: “Duke Energy agreed to commercially reasonable efforts to achieve 44.0 MW of service by April 2026”
How we checked this
Checked on October 11, 2026. The cited source supports every part of this claim.
A footnote on the NC-1 site overview states that, under the Duke Energy Capacity Agreement, Duke agreed to commercially reasonable efforts to reach 44.0 MW of service by April 2026.
Confirmed in the source:
- Duke Energy agreed to commercially reasonable efforts to achieve 44.0 MW of service by April 2026
- The Duke Energy agreement relates to NC-1
What we did: Read our cached copy of SEC EDGAR (8-K Ex) (https://www.sec.gov/Archives/edgar/data/2042022/000121390026007474/ea027401701ex99-1_white.htm) in full (23,241 characters, retrieved September 21, 2026) and checked each assertion in the claim against it.
Additional evidence
confirms whitefiber 8-K exhibit (ea027401701ex99-1_white.htm)
Quote: “Duke Energy agreed to commercially reasonable efforts to achieve 44.0 MW of service by April 2026”
confirms WhiteFiber 10-K filed 2026-03-26
Quote: “we intend to complete the first 27 gross MW (gross) of service at NC-1 in April 2026, with another 27 gross MW (gross) of service in May 2026”
confirms whitefiber 8-K exhibit (ea029430601ex99-1.htm)
Quote: “Duke Energy has completed the work required to deliver the initial 54 gross MW of utility power to the NC-1 site.”