NC1 Phase 3 potential additional capacity

Company: WhiteFiber - Project: NC-1

Subject kind
facility capacity
Statement date
2026-08-14
Promised amount
200.0 MW
Current status
stated

The claim, verbatim

Company working with Duke Energy to evaluate potential delivery of additional 200 megawatts of incremental power at NC1, which could bring site to approximately 300 gross megawatts, subject to Duke Energy utility process

Source (primary)

White Fiber (WYFI) Q2 2026 Earnings Call: NC1 Ramp and $540M+ Cloud Deals - TradingKey (-, news_article)
View cached copy (2026-08-31)Live source ↗

Quote: “we are working with Duke Energy in further evaluating the potential delivery of an additional 200 megawatts of incremental power to the site... would bring NC1 to approximately 300 gross megawatts. This is a longer-term opportunity and remains subject to the utility process”

How we checked this

Checked on September 19, 2026. The cited source supports every part of this claim.

Management describes working with Duke Energy on a potential additional 200 megawatts that could bring NC1 to approximately 300 gross megawatts, subject to the utility process.

Confirmed in the source:

What we did: Read our cached copy of the publisher (https://www.tradingkey.com/news/transcripts/262107202-tradingkey) in full (70,978 characters, retrieved August 31, 2026) and checked each assertion in the claim against it.

Additional evidence

confirms White Fiber (WYFI) Q2 2026 Earnings Call: NC1 Ramp and $540M+ Cloud Deals - TradingKey

Quote: “we are working with Duke Energy in further evaluating the potential delivery of an additional 200 megawatts of incremental power to the site... would bring NC1 to approximately 300 gross megawatts. This is a longer-term opportunity and remains subject to the utility process”

View cached copy (2026-08-31)Live source ↗