NC-1 operational IT capacity
Company: WhiteFiber
The claim, verbatim
NC-1 has approximately 35 MW of operational IT capacity out of 40 MW contracted.
Source (primary)
WhiteFiber Completes Acquisition of Two North Carolina Data Center Development Sites and Provides NC-1 Update - Quantisnow (-, news_article)
View cached copy (2026-11-04)Live source ↗
Quote: “NC-1 operational IT capacity approximately 35 MW of 40 MW contracted”
How we checked this
This claim has not yet been checked assertion-by-assertion against its source. It carries a cited source and quote, but the deeper check has not run. When it does, the result appears here whatever it says.
Additional evidence
confirms WhiteFiber Completes Acquisition of Two North Carolina Data Center Development Sites and Provides NC-1 Update - Quantisnow
Quote: “NC-1 operational IT capacity approximately 35 MW of 40 MW contracted”
confirms WhiteFiber (WYFI) Buys Two Data Center Sites for $60M; NC-1 Ramp Delayed - TradingView
Quote: “At NC-1, about 35 MW of a contracted 40 MW IT deployment is operational”