jain.com

NC-1 conditional purchase price increase (per-MW over 99 MW threshold)

Company: WhiteFiber - Project: NC-1

Subject kind
financing
Statement date
2026-03-25
Promised by
2029-05-20
Promised amount
5.0 USD
Current status
stated

The claim, verbatim

NC-1 purchase price increases by $200,000 per MW over 99 MW (max $5 million) if Duke delivers within 4 years of May 20, 2025

Source (primary)

WhiteFiber 10-K filed 2026-03-26 (SEC EDGAR, sec_filing)
View cached copy (2026-08-31)Live source ↗

Quote: “Additionally, the purchase price will increase by an additional $200,000 per MW over 99 MW (gross) up to a maximum of $5 million if at least 99 MW (gross) are actually delivered, or Duke Energy provides an Electric Services Agreement for the provision of at least 99 MW (gross), within four years of May 20, 2025.”

How we checked this

This claim has not yet been checked assertion-by-assertion against its source. It carries a cited source and quote, but the deeper check has not run. When it does, the result appears here whatever it says.

Additional evidence

confirms WhiteFiber 10-K filed 2026-03-26

Quote: “Additionally, the purchase price will increase by an additional $200,000 per MW over 99 MW (gross) up to a maximum of $5 million if at least 99 MW (gross) are actually delivered, or Duke Energy provides an Electric Services Agreement for the provision of at least 99 MW (gross), within four years of May 20, 2025.”

View cached copy (2026-08-31)Live source ↗