NC-1 40 MW cumulative capacity by Q2 2026
Company: WhiteFiber - Project: NC-1
What the later record shows
Delivered on time · happened May 31, 2026
The June 9 investor presentation, citing company information as of May 31, 2026, says Duke Energy had completed the work to deliver 54 gross MW of utility power to NC-1. That exceeds the 40 MW gross promised by the end of Q2 2026, though the passage does not use the word 'energized'.
“Duke Energy has completed the work required to deliver the initial 54 gross MW of utility power to the NC-1 site.”
2026-06-09 · whitefiber 8-K exhibit (ea029430601ex99-1.htm) View cached copy (2026-09-06)Live source ↗
Checked October 10, 2026 against filings, releases and reporting published after the claim was made. Quotes are verbatim from the linked documents.
The claim, verbatim
Management expects an incremental 16 MW (gross) will be energized in the second quarter of 2026 for a total of 40 MW (gross) at NC-1 by end of Q2 2026
Source (primary)
WhiteFiber S-1/A filed 2025-07-29 (SEC EDGAR, sec_filing)
View cached copy (2026-08-31)Live source ↗
Quote: “an incremental 16 MW (gross) will be energized in the second quarter of 2026 for a total of 40 MW (gross) at the NC-1 site by the end of the second quarter of 2026.”
How we checked this
Checked on October 11, 2026. The cited source supports every part of this claim.
The prospectus states that management expects an incremental 16 MW (gross) to be energized in Q2 2026, for a total of 40 MW (gross) at NC-1 by the end of that quarter.
Confirmed in the source:
- Management expects an incremental 16 MW (gross) to be energized in the second quarter of 2026
- That would bring NC-1 to a total of 40 MW (gross) by the end of the second quarter of 2026
What we did: Read our cached copy of SEC EDGAR (https://www.sec.gov/Archives/edgar/data/2042022/000121390025068434/ea0249945-03.htm) in full (841,778 characters, retrieved August 31, 2026) and checked each assertion in the claim against it.
Additional evidence
confirms WhiteFiber S-1/A filed 2025-07-29
Quote: “an incremental 16 MW (gross) will be energized in the second quarter of 2026 for a total of 40 MW (gross) at the NC-1 site by the end of the second quarter of 2026.”
confirms whitefiber 8-K exhibit (ea029430601ex99-1.htm)
Quote: “Duke Energy has completed the work required to deliver the initial 54 gross MW of utility power to the NC-1 site.”