NC-1 40 MW cumulative capacity by Q2 2026

Company: WhiteFiber - Project: NC-1

Subject kind
facility capacity
Statement date
2025-07-28
Promised by
2026-06-30
Promised amount
40.0 MW
Current status
verified

What the later record shows

Delivered on time · happened May 31, 2026

The June 9 investor presentation, citing company information as of May 31, 2026, says Duke Energy had completed the work to deliver 54 gross MW of utility power to NC-1. That exceeds the 40 MW gross promised by the end of Q2 2026, though the passage does not use the word 'energized'.

“Duke Energy has completed the work required to deliver the initial 54 gross MW of utility power to the NC-1 site.”
2026-06-09 · whitefiber 8-K exhibit (ea029430601ex99-1.htm) View cached copy (2026-09-06)Live source ↗

Checked October 10, 2026 against filings, releases and reporting published after the claim was made. Quotes are verbatim from the linked documents.

The claim, verbatim

Management expects an incremental 16 MW (gross) will be energized in the second quarter of 2026 for a total of 40 MW (gross) at NC-1 by end of Q2 2026

Source (primary)

WhiteFiber S-1/A filed 2025-07-29 (SEC EDGAR, sec_filing)
View cached copy (2026-08-31)Live source ↗

Quote: “an incremental 16 MW (gross) will be energized in the second quarter of 2026 for a total of 40 MW (gross) at the NC-1 site by the end of the second quarter of 2026.”

How we checked this

Checked on October 11, 2026. The cited source supports every part of this claim.

The prospectus states that management expects an incremental 16 MW (gross) to be energized in Q2 2026, for a total of 40 MW (gross) at NC-1 by the end of that quarter.

Confirmed in the source:

What we did: Read our cached copy of SEC EDGAR (https://www.sec.gov/Archives/edgar/data/2042022/000121390025068434/ea0249945-03.htm) in full (841,778 characters, retrieved August 31, 2026) and checked each assertion in the claim against it.

Additional evidence

confirms WhiteFiber S-1/A filed 2025-07-29

Quote: “an incremental 16 MW (gross) will be energized in the second quarter of 2026 for a total of 40 MW (gross) at the NC-1 site by the end of the second quarter of 2026.”

View cached copy (2026-08-31)Live source ↗

confirms whitefiber 8-K exhibit (ea029430601ex99-1.htm)

Quote: “Duke Energy has completed the work required to deliver the initial 54 gross MW of utility power to the NC-1 site.”

View cached copy (2026-09-06)Live source ↗

Record of changes

September 2, 2026 — stated
Automated extraction from the cited source. Recorded automatically from the cited source when it was published, then queued for evidence review.
September 3, 2026 — delayed
Automated extraction from the cited source. Recorded automatically from the cited source when it was published, then queued for evidence review.
October 9, 2026 — outcome unconfirmed
Automated extraction from the cited source. Recorded automatically from the cited source when it was published, then queued for evidence review.
October 10, 2026 — verified
Automated extraction from the cited source. Recorded automatically from the cited source when it was published, then queued for evidence review.