NC-1 second 20 MW ready-for-service

Company: WhiteFiber - Project: NC-1

This claim was marked delayed on October 10, 2026. Recorded automatically from the cited source when it was published, then queued for evidence review.

How this was decided: Automated extraction from the cited source. The claim is preserved below exactly as it was originally published, so the record shows what was asserted as well as what became of it.

Subject kind
facility timeline
Statement date
2025-12-17
Promised by
2026-05-30
Promised amount
20.0 MW
Current status
delayed

What the later record shows

The date slipped · new target August 31, 2026

Only about 20 MW was available by the August 2026 call, so the remaining 20 MW was not billing by May 30, 2026. Management then expected full 40 MW run-rate billing by the end of August, and no passage confirms it was reached.

“Samir Tabar, chief executive officer, said about 20 megawatts of IT capacity at NC-1 was available for customer installation and testing.”
2026-08-13 · WYFI Q2 Earnings Call Focuses on NC-1 Ramp and Cloud Expansion - Yahoo Finance View cached copy (2026-08-31)Live source ↗
“Samir Tabar, the CEO, mentioned that initial billing commenced and expected the full 40 MW to have reached run-rate billing by the end of August.”
2026-09-30 · WYFI Stock Rallies 56% in 6 Months: Here's What You Should Know - Zacks Investment Research View cached copy (2026-10-01)Live source ↗Archive.org ↗

Checked October 10, 2026 against filings, releases and reporting published after the claim was made. Quotes are verbatim from the linked documents.

The claim, verbatim

Billing for the remaining 20 MW of NC-1 is targeted to commence May 30, 2026

Source (primary)

whitefiber 8-K exhibit (ea026991801ex99-1_white.htm) (SEC EDGAR (8-K Ex), press_release)
View cached copy (2026-09-23)Live source ↗

Quote: “with the remaining 20 MW targeted to commence May 30, 2026”

How we checked this

Checked on October 12, 2026. The cited source supports every part of this claim.

The press release states that billing for the remaining 20 MW at NC-1 is targeted to commence May 30, 2026.

Confirmed in the source:

What we did: Read our cached copy of SEC EDGAR (8-K Ex) (https://www.sec.gov/Archives/edgar/data/2042022/000121390025123321/ea026991801ex99-1_white.htm) in full (8,218 characters, retrieved September 23, 2026) and checked each assertion in the claim against it.

Additional evidence

confirms whitefiber 8-K exhibit (ea026991801ex99-1_white.htm)

Quote: “with the remaining 20 MW targeted to commence May 30, 2026”

View cached copy (2026-09-23)Live source ↗

delays WYFI Q2 Earnings Call Focuses on NC-1 Ramp and Cloud Expansion - Yahoo Finance

Quote: “Samir Tabar, chief executive officer, said about 20 megawatts of IT capacity at NC-1 was available for customer installation and testing.”

View cached copy (2026-08-31)Live source ↗

delays WYFI Stock Rallies 56% in 6 Months: Here's What You Should Know - Zacks Investment Research

Quote: “Samir Tabar, the CEO, mentioned that initial billing commenced and expected the full 40 MW to have reached run-rate billing by the end of August.”

View cached copy (2026-10-01)Live source ↗Archive.org ↗

Record of changes

September 23, 2026 — stated
Automated extraction from the cited source. Recorded automatically from the cited source when it was published, then queued for evidence review.
September 24, 2026 — delayed
Automated extraction from the cited source. Recorded automatically from the cited source when it was published, then queued for evidence review.
October 9, 2026 — outcome unconfirmed
Automated extraction from the cited source. Recorded automatically from the cited source when it was published, then queued for evidence review.
October 10, 2026 — delayed
Automated extraction from the cited source. Recorded automatically from the cited source when it was published, then queued for evidence review.