NC-1 second 20 MW ready-for-service

Company: WhiteFiber - Project: NC-1

This claim was marked delayed on September 24, 2026. Recorded automatically from the cited source when it was published, then queued for evidence review.

How this was decided: Automated extraction from the cited source. The claim is preserved below exactly as it was originally published, so the record shows what was asserted as well as what became of it.

Subject kind
facility timeline
Statement date
2025-12-17
Promised by
2026-05-30
Promised amount
20.0 MW
Current status
delayed

The claim, verbatim

Billing for the remaining 20 MW of NC-1 is targeted to commence May 30, 2026

Source (primary)

whitefiber 8-K exhibit (ea026991801ex99-1_white.htm) (SEC EDGAR (8-K Ex), press_release)
View cached copy (2026-09-23)Live source ↗

Quote: “with the remaining 20 MW targeted to commence May 30, 2026”

How we checked this

This claim has not yet been checked assertion-by-assertion against its source. It carries a cited source and quote, but the deeper check has not run. When it does, the result appears here whatever it says.

Additional evidence

confirms whitefiber 8-K exhibit (ea026991801ex99-1_white.htm)

Quote: “with the remaining 20 MW targeted to commence May 30, 2026”

View cached copy (2026-09-23)Live source ↗

Record of changes

September 23, 2026 — stated
Automated extraction from the cited source. Recorded automatically from the cited source when it was published, then queued for evidence review.
September 24, 2026 — delayed
Automated extraction from the cited source. Recorded automatically from the cited source when it was published, then queued for evidence review.