Duke Energy capacity agreement - Phase 2
Company: WhiteFiber - Project: NC-1
What the later record shows
Delivered; the record does not say when
Duke had completed work to deliver 54 gross MW by the June 2026 deck, but no passage dates when 40 MW of service was reached relative to April 1, 2026.
“Duke Energy has completed the work required to deliver the initial 54 gross MW of utility power to the NC-1 site.”
2026-06-09 · whitefiber 8-K exhibit (ea029430601ex99-1.htm) View cached copy (2026-09-06)Live source ↗
Checked October 10, 2026 against filings, releases and reporting published after the claim was made. Quotes are verbatim from the linked documents.
The claim, verbatim
Duke Energy agreed to use commercially reasonable efforts to achieve 40 MW (gross) of service to NC-1 property by April 1, 2026
Source (primary)
WhiteFiber S-1/A filed 2025-07-29 (SEC EDGAR, sec_filing)
View cached copy (2026-08-31)Live source ↗
Quote: “Pursuant to a Capacity Agreement between Enovum and Duke Energy, Duke Energy agreed to use commercially reasonable efforts to achieve 40 MW (gross) of service to the Property by April 1, 2026”
How we checked this
Checked on October 11, 2026. The cited source supports every part of this claim.
The prospectus states that Duke Energy agreed to use commercially reasonable efforts to achieve 40 MW (gross) of service to the NC-1 property by April 1, 2026.
Confirmed in the source:
- Duke Energy agreed under the Capacity Agreement to use commercially reasonable efforts to provide service to the NC-1 property
- The target is 40 MW (gross) by April 1, 2026
What we did: Read our cached copy of SEC EDGAR (https://www.sec.gov/Archives/edgar/data/2042022/000121390025068434/ea0249945-03.htm) in full (841,778 characters, retrieved August 31, 2026) and checked each assertion in the claim against it.
Additional evidence
confirms WhiteFiber S-1/A filed 2025-07-29
Quote: “Pursuant to a Capacity Agreement between Enovum and Duke Energy, Duke Energy agreed to use commercially reasonable efforts to achieve 40 MW (gross) of service to the Property by April 1, 2026”
confirms whitefiber 8-K exhibit (ea029430601ex99-1.htm)
Quote: “Duke Energy has completed the work required to deliver the initial 54 gross MW of utility power to the NC-1 site.”