Duke Energy capacity agreement - Phase 2

Company: WhiteFiber - Project: NC-1

Subject kind
partnership
Statement date
2025-07-28
Promised by
2026-04-01
Promised amount
40.0 MW
Current status
verified

What the later record shows

Delivered; the record does not say when

Duke had completed work to deliver 54 gross MW by the June 2026 deck, but no passage dates when 40 MW of service was reached relative to April 1, 2026.

“Duke Energy has completed the work required to deliver the initial 54 gross MW of utility power to the NC-1 site.”
2026-06-09 · whitefiber 8-K exhibit (ea029430601ex99-1.htm) View cached copy (2026-09-06)Live source ↗

Checked October 10, 2026 against filings, releases and reporting published after the claim was made. Quotes are verbatim from the linked documents.

The claim, verbatim

Duke Energy agreed to use commercially reasonable efforts to achieve 40 MW (gross) of service to NC-1 property by April 1, 2026

Source (primary)

WhiteFiber S-1/A filed 2025-07-29 (SEC EDGAR, sec_filing)
View cached copy (2026-08-31)Live source ↗

Quote: “Pursuant to a Capacity Agreement between Enovum and Duke Energy, Duke Energy agreed to use commercially reasonable efforts to achieve 40 MW (gross) of service to the Property by April 1, 2026”

How we checked this

Checked on October 11, 2026. The cited source supports every part of this claim.

The prospectus states that Duke Energy agreed to use commercially reasonable efforts to achieve 40 MW (gross) of service to the NC-1 property by April 1, 2026.

Confirmed in the source:

What we did: Read our cached copy of SEC EDGAR (https://www.sec.gov/Archives/edgar/data/2042022/000121390025068434/ea0249945-03.htm) in full (841,778 characters, retrieved August 31, 2026) and checked each assertion in the claim against it.

Additional evidence

confirms WhiteFiber S-1/A filed 2025-07-29

Quote: “Pursuant to a Capacity Agreement between Enovum and Duke Energy, Duke Energy agreed to use commercially reasonable efforts to achieve 40 MW (gross) of service to the Property by April 1, 2026”

View cached copy (2026-08-31)Live source ↗

confirms whitefiber 8-K exhibit (ea029430601ex99-1.htm)

Quote: “Duke Energy has completed the work required to deliver the initial 54 gross MW of utility power to the NC-1 site.”

View cached copy (2026-09-06)Live source ↗

Record of changes

September 2, 2026 — stated
Automated extraction from the cited source. Recorded automatically from the cited source when it was published, then queued for evidence review.
September 3, 2026 — delayed
Automated extraction from the cited source. Recorded automatically from the cited source when it was published, then queued for evidence review.
October 9, 2026 — outcome unconfirmed
Automated extraction from the cited source. Recorded automatically from the cited source when it was published, then queued for evidence review.
October 10, 2026 — verified
Automated extraction from the cited source. Recorded automatically from the cited source when it was published, then queued for evidence review.