NC-1 initial 24 MW completion
Company: WhiteFiber - Project: NC-1
What the later record shows
Delivered late · new target April 30, 2026
The March 2026 10-K pushed the first NC-1 phase to April 2026, after Q1. Later reports show capacity in use and billing begun, with no exact completion date given.
“we intend to complete the first 27 gross MW (gross) of service at NC-1 in April 2026, with another 27 gross MW (gross) of service in May 2026”
2026-03-25 · WhiteFiber 10-K filed 2026-03-26 View cached copy (2026-08-31)Live source ↗
“WYFI held approximately 20 MW of IT capacity to support installation and testing activities of Nscale and its investment-grade offtaker”
2026-09-30 · WYFI Stock Rallies 56% in 6 Months: Here's What You Should Know - Zacks Investment Research View cached copy (2026-10-01)Live source ↗Archive.org ↗
Checked October 10, 2026 against filings, releases and reporting published after the claim was made. Quotes are verbatim from the linked documents.
The claim, verbatim
Initial capacity of 24 MW for NC-1 estimated to be completed and operational in Q1 2026
Source (primary)
WhiteFiber S-1 filed 2025-07-11 (SEC EDGAR, sec_filing)
View cached copy (2026-08-31)Live source ↗
Quote: “We estimate that the initial capacity of 24 MW (gross) for the NC-1 site will be completed and operational in the first quarter of 2026.”
How we checked this
Checked on October 11, 2026. The cited source supports every part of this claim.
The filing states that the initial 24 MW (gross) capacity at NC-1 is estimated to be completed and operational in Q1 2026.
Confirmed in the source:
- WhiteFiber estimates the initial 24 MW (gross) capacity at NC-1 will be completed and operational in the first quarter of 2026
What we did: Read our cached copy of SEC EDGAR (https://www.sec.gov/Archives/edgar/data/2042022/000121390025063338/ea0248382-s1_white.htm) in full (819,180 characters, retrieved August 31, 2026) and checked each assertion in the claim against it.
Additional evidence
confirms WhiteFiber S-1 filed 2025-07-11
Quote: “We estimate that the initial capacity of 24 MW (gross) for the NC-1 site will be completed and operational in the first quarter of 2026.”
confirms WhiteFiber 10-K filed 2026-03-26
Quote: “we intend to complete the first 27 gross MW (gross) of service at NC-1 in April 2026, with another 27 gross MW (gross) of service in May 2026”
confirms WYFI Stock Rallies 56% in 6 Months: Here's What You Should Know - Zacks Investment Research
Quote: “WYFI held approximately 20 MW of IT capacity to support installation and testing activities of Nscale and its investment-grade offtaker”