NC-1 40 MW Duke power by Apr 2026

Company: WhiteFiber - Project: NC-1

Subject kind
facility timeline
Statement date
2025-08-27
Promised by
2026-04-30
Promised amount
40.0 MW
Current status
verified

What the later record shows

Delivered; the record does not say when

A June 2026 investor deck, with information as of May 31, 2026, says Duke Energy has completed the work to deliver the initial 54 gross MW to NC-1. That exceeds 40 MW, but no passage says whether this happened by April 2026.

“Duke Energy has completed the work required to deliver the initial 54 gross MW of utility power to the NC-1 site.”
2026-06-09 · whitefiber 8-K exhibit (ea029430601ex99-1.htm) View cached copy (2026-09-06)Live source ↗
“Source: Company information as of May 31, 2026”
2026-06-09 · whitefiber 8-K exhibit (ea029430601ex99-1.htm) View cached copy (2026-09-06)Live source ↗

Checked October 10, 2026 against filings, releases and reporting published after the claim was made. Quotes are verbatim from the linked documents.

The claim, verbatim

Under the Duke Energy Capacity Agreement, Duke agreed to commercially reasonable efforts to deliver 40.0 MW of service to NC-1 by April 2026.

Source (primary)

whitefiber 8-K exhibit (ea025484401ex99-1_white.htm) (SEC EDGAR (8-K Ex), press_release)
View cached copy (2026-10-05)Live source ↗

Quote: “40.0 MW by April 2026”

How we checked this

Checked on October 12, 2026. The cited source supports every part of this claim.

The same NC-1 footnote lists '40.0 MW by April 2026' as part of Duke Energy's commercially-reasonable-efforts commitment.

Confirmed in the source:

What we did: Read our cached copy of SEC EDGAR (8-K Ex) (https://www.sec.gov/Archives/edgar/data/2042022/000121390025081421/ea025484401ex99-1_white.htm) in full (24,103 characters, retrieved October 5, 2026) and checked each assertion in the claim against it.

Additional evidence

confirms whitefiber 8-K exhibit (ea025484401ex99-1_white.htm)

Quote: “40.0 MW by April 2026”

View cached copy (2026-10-05)Live source ↗

confirms whitefiber 8-K exhibit (ea029430601ex99-1.htm)

Quote: “Duke Energy has completed the work required to deliver the initial 54 gross MW of utility power to the NC-1 site.”

View cached copy (2026-09-06)Live source ↗

Record of changes

October 5, 2026 — stated
Automated extraction from the cited source. Recorded automatically from the cited source when it was published, then queued for evidence review.
October 6, 2026 — delayed
Automated extraction from the cited source. Recorded automatically from the cited source when it was published, then queued for evidence review.
October 9, 2026 — outcome unconfirmed
Automated extraction from the cited source. Recorded automatically from the cited source when it was published, then queued for evidence review.
October 10, 2026 — verified
Automated extraction from the cited source. Recorded automatically from the cited source when it was published, then queued for evidence review.