NC-1: ~35 MW of contracted 40 MW IT deployment operational

Company: WhiteFiber

Subject kind
facility capacity
Statement date
2026-11-03
Promised amount
40.0 MW
Current status
stated

The claim, verbatim

About 35 MW of NC-1's contracted 40 MW IT deployment is operational. Work continues to bring the remaining 5 MW online.

Source (primary)

WhiteFiber Buys Two North Carolina Sites for Data Center Retrofits - Unite.AI (-, news_article)
View cached copy (2026-11-04)Live source ↗Archive.org ↗

Quote: “approximately 35 MW of the contracted 40 MW IT deployment is operational, while work continues to bring the remaining 5 MW online”

How we checked this

This claim has not yet been checked assertion-by-assertion against its source. It carries a cited source and quote, but the deeper check has not run. When it does, the result appears here whatever it says.

Additional evidence

confirms WhiteFiber Buys Two North Carolina Sites for Data Center Retrofits - Unite.AI

Quote: “approximately 35 MW of the contracted 40 MW IT deployment is operational, while work continues to bring the remaining 5 MW online”