NC-1 99 MW total capacity target

Company: WhiteFiber - Project: NC-1

Subject kind
facility capacity
Statement date
2026-01-25
Promised by
2030-01-25
Promised amount
99.0 MW
Current status
stated

The claim, verbatim

NC-1 is targeted to reach 99 MW gross capacity within four years

Source (primary)

whitefiber 8-K exhibit (ea027401701ex99-1_white.htm) (SEC EDGAR (8-K Ex), press_release)
View cached copy (2026-09-21)Live source ↗

Quote: “99 Gross MW... Total Target Expanded Gross Capacity... 99.0 MW within four years”

How we checked this

Checked on September 25, 2026. The cited source supports every part of this claim.

The document repeatedly states total NC-1 power capacity of at least 99.0 gross MW within four years.

Confirmed in the source:

What we did: Read our cached copy of SEC EDGAR (8-K Ex) (https://www.sec.gov/Archives/edgar/data/2042022/000121390026007474/ea027401701ex99-1_white.htm) in full (23,241 characters, retrieved September 21, 2026) and checked each assertion in the claim against it.

Additional evidence

confirms whitefiber 8-K exhibit (ea027401701ex99-1_white.htm)

Quote: “99 Gross MW... Total Target Expanded Gross Capacity... 99.0 MW within four years”

View cached copy (2026-09-21)Live source ↗