jain.com

NC-1 full 40 MW run-rate billing by end of August

Company: WhiteFiber - Project: NC-1

Subject kind
facility timeline
Statement date
2026-09-30
Promised by
2026-08-31
Promised amount
40.0 MW
Current status
outcome unconfirmed

What the later record shows

The date slipped

The November 2026 update says full 40 MW run-rate billing was delayed past August by switchgear issues. Only about 35 MW was operational, and no revised date was named.

“delayed NC-1’s ramp to full contracted run-rate billing beyond the previously anticipated August timeframe”
2026-11-02 · whitefiber 8-K exhibit (ea031063901ex99-1.htm) View cached copy (2026-11-04)Live source ↗
“During its second-quarter earnings call in August, WhiteFiber said it expected the entire contracted deployment to reach full run-rate billing by the end of that month. That milestone has not yet been achieved.”
2026-11-03 · WhiteFiber Closes $60M Data Center Acquisition as NC-1 Delays Full Revenue Ramp - TheEnergyMag View cached copy (2026-11-04)Live source ↗Archive.org ↗

Checked November 9, 2026 against filings, releases and reporting published after the claim was made. Quotes are verbatim from the linked documents.

The claim, verbatim

CEO said initial billing commenced and expected the full 40 MW to reach run-rate billing by the end of August.

Source (primary)

WYFI Stock Rallies 56% in 6 Months: Here's What You Should Know - TradingView (-, news_article)
View cached copy (2026-10-01)Live source ↗Archive.org ↗

Quote: “initial billing commenced and expected the full 40 MW to have reached run-rate billing by the end of August”

How we checked this

Checked on November 10, 2026. The cited source supports every part of this claim.

The article reports that CEO Samir Tabar said initial billing had commenced at NC-1 and that he expected the full 40 MW to reach run-rate billing by the end of August, which matches every part of the claim.

Confirmed in the source:

What we did: Read our cached copy of the publisher (https://www.tradingview.com/news/zacks:8751f15c7094b:0-wyfi-stock-rallies-56-in-6-months-here-s-what-you-should-know/) in full (6,899 characters, retrieved October 1, 2026) and checked each assertion in the claim against it.

Additional evidence

confirms WYFI Stock Rallies 56% in 6 Months: Here's What You Should Know - TradingView

Quote: “initial billing commenced and expected the full 40 MW to have reached run-rate billing by the end of August”

View cached copy (2026-10-01)Live source ↗Archive.org ↗

confirms WYFI Stock Rallies 56% in 6 Months: Here's What You Should Know - Zacks Investment Research

Quote: “Samir Tabar, the CEO, mentioned that initial billing commenced and expected the full 40 MW to have reached run-rate billing by the end of August.”

View cached copy (2026-10-01)Live source ↗Archive.org ↗

confirms WYFI Stock Rallies 56% in 6 Months: Here's What You Should Know - Zacks Investment Research

Quote: “Samir Tabar, the CEO, mentioned that initial billing commenced and expected the full 40 MW to have reached run-rate billing by the end of August.”

View cached copy (2026-10-03)Live source ↗Archive.org ↗

confirms WYFI Stock Rallies 56% in 6 Months: Here's What You Should Know - The Globe and Mail

Quote: “initial billing commenced and expected the full 40 MW to have reached run-rate billing by the end of August”

View cached copy (2026-10-05)Live source ↗Archive.org ↗

confirms WYFI Stock Rallies 56% in 6 Months: Here's What You Should Know - The Globe and Mail

Quote: “initial billing commenced and expected the full 40 MW to have reached run-rate billing by the end of August”

View cached copy (2026-10-06)Live source ↗Archive.org ↗

delays whitefiber 8-K exhibit (ea031063901ex99-1.htm)

Quote: “delayed NC-1’s ramp to full contracted run-rate billing beyond the previously anticipated August timeframe”

View cached copy (2026-11-04)Live source ↗

delays WhiteFiber Closes $60M Data Center Acquisition as NC-1 Delays Full Revenue Ramp - TheEnergyMag

Quote: “During its second-quarter earnings call in August, WhiteFiber said it expected the entire contracted deployment to reach full run-rate billing by the end of that month. That milestone has not yet been achieved.”

View cached copy (2026-11-04)Live source ↗Archive.org ↗

Record of changes

October 1, 2026 — stated
Automated extraction from the cited source. Recorded automatically from the cited source when it was published, then queued for evidence review.
October 2, 2026 — delayed
Automated extraction from the cited source. Recorded automatically from the cited source when it was published, then queued for evidence review.
October 9, 2026 — outcome unconfirmed
Automated extraction from the cited source. Recorded automatically from the cited source when it was published, then queued for evidence review.