NC-1 35 of 40 MW IT operational
Company: WhiteFiber
The claim, verbatim
Approximately 35 MW of the contracted 40 MW IT deployment at NC-1 is operational, with work ongoing to bring the remaining 5 MW online; switchgear commissioning issues delayed the ramp beyond the previously anticipated August timeframe.
Source (primary)
whitefiber 8-K exhibit (ea031063901ex99-1.htm) (SEC EDGAR (8-K Ex), press_release)
View cached copy (2026-11-04)Live source ↗
Quote: “Approximately 35 MW of the contracted 40 MW IT deployment is now operational, with work ongoing to bring the remaining 5 MW online.”
How we checked this
This claim has not yet been checked assertion-by-assertion against its source. It carries a cited source and quote, but the deeper check has not run. When it does, the result appears here whatever it says.
Additional evidence
confirms whitefiber 8-K exhibit (ea031063901ex99-1.htm)
Quote: “Approximately 35 MW of the contracted 40 MW IT deployment is now operational, with work ongoing to bring the remaining 5 MW online.”