jain.com

NC1 data center billing capacity

Company: WhiteFiber - Project: NC-1

Subject kind
facility capacity
Statement date
2026-08-14
Promised by
2026-08-31
Promised amount
40.0 MW
Current status
not yet verifiable

The claim, verbatim

The full 40 MW contracted load at NC1 will be billing by the end of August.

Source (primary)

WhiteFiber (WYFI) Stock Faces Margin Strain Despite Fast Revenue Growth - simplywall.st (-, news_article)
View cached copy (2026-08-31)Live source ↗

Quote: “management expects the full 40 MW contracted load to be billing by the end of August”

How we checked this

This claim has not yet been checked assertion-by-assertion against its source. It carries a cited source and quote, but the deeper check has not run. When it does, the result appears here whatever it says.

Additional evidence

confirms WhiteFiber (WYFI) Stock Faces Margin Strain Despite Fast Revenue Growth - simplywall.st

Quote: “management expects the full 40 MW contracted load to be billing by the end of August”

View cached copy (2026-08-31)Live source ↗

Record of changes

September 5, 2026 — stated
Automated extraction from the cited source. Recorded automatically from the cited source when it was published, then queued for evidence review.
September 6, 2026 — not yet verifiable
Automated extraction from the cited source. Recorded automatically from the cited source when it was published, then queued for evidence review.