Duke Energy - 24 MW

Company: WhiteFiber - Project: NC-1

This claim was marked delayed on September 3, 2026. Recorded automatically from the cited source when it was published, then queued for evidence review.

How this was decided: Automated extraction from the cited source. The claim is preserved below exactly as it was originally published, so the record shows what was asserted as well as what became of it.

Subject kind
partnership
Statement date
2025-07-22
Promised by
2025-09-01
Promised amount
24.0 MW
Current status
delayed

The claim, verbatim

Duke Energy agreed to use commercially reasonable efforts to provide 24 MW (gross) of power service to NC-1 property by September 1, 2025

Source (primary)

WhiteFiber S-1/A filed 2025-07-23 (SEC EDGAR, sec_filing)
View cached copy (2026-08-31)Live source ↗

Quote: “Pursuant to a Capacity Agreement between Enovum and Duke Energy, Duke Energy agreed to use commercially reasonable efforts to achieve 24 MW (gross) of service to the Property by September 1, 2025”

How we checked this

This claim has not yet been checked assertion-by-assertion against its source. It carries a cited source and quote, but the deeper check has not run. When it does, the result appears here whatever it says.

Additional evidence

confirms WhiteFiber S-1/A filed 2025-07-23

Quote: “Pursuant to a Capacity Agreement between Enovum and Duke Energy, Duke Energy agreed to use commercially reasonable efforts to achieve 24 MW (gross) of service to the Property by September 1, 2025”

View cached copy (2026-08-31)Live source ↗

Record of changes

September 2, 2026 — stated
Automated extraction from the cited source. Recorded automatically from the cited source when it was published, then queued for evidence review.
September 3, 2026 — delayed
Automated extraction from the cited source. Recorded automatically from the cited source when it was published, then queued for evidence review.