NC-1 Phase 1 capacity in April and May 2026
Company: WhiteFiber - Project: NC-1
The claim, verbatim
NC-1 Phase 1 capacity will be delivered in two tranches: 20 MW in April 2026 and 20 MW in May 2026
Source (primary)
whitefiber 8-K exhibit (ea027401701ex99-1_white.htm) (SEC EDGAR (8-K Ex), press_release)
View cached copy (2026-09-21)Live source ↗
Quote: “20 MW expected in April 2026 and 20 MW expected in May 2026”
How we checked this
Checked on September 25, 2026. The cited source supports part of this claim, but not all of it.
The presentation gives the 20 MW April and 20 MW May 2026 schedule for the 40 MW Nscale IT load. It describes that 40 MW as Phase 1 & 2 capacity, not Phase 1 alone, and calls the dates expectations.
Confirmed in the source:
- 20 MW of NC-1 capacity is expected in April 2026
- 20 MW of NC-1 capacity is expected in May 2026
We could not confirm this from the cited source:
- That these two tranches make up NC-1 Phase 1 capacity (the document ties the 40 MW to Phase 1 & 2 combined)
- That delivery is certain rather than expected
That does not mean it is false — only that this source does not establish it, as of the date above. If we find a source that settles it, we will re-check and update this page.
What we did: Read our cached copy of SEC EDGAR (8-K Ex) (https://www.sec.gov/Archives/edgar/data/2042022/000121390026007474/ea027401701ex99-1_white.htm) in full (23,241 characters, retrieved September 21, 2026) and checked each assertion in the claim against it.
Additional evidence
confirms whitefiber 8-K exhibit (ea027401701ex99-1_white.htm)
Quote: “20 MW expected in April 2026 and 20 MW expected in May 2026”