NC-1 Phase 1 capacity in April and May 2026
Company: WhiteFiber - Project: NC-1
What the later record shows
Partly delivered
The two 20 MW tranches were due by May 2026. In August 2026 the CEO still described the first phase of NC-1 as being completed, and a November 2026 news report says only about 35 MW of the contracted 40 MW was operational, with switchgear issues causing delays.
“provides greater capital certainty as we complete the first phase of NC-1 and prepare for the next phase of WhiteFiber’s colocation growth”
2026-08-20 · whitefiber 8-K exhibit (ea030292501ex99-3.htm) View cached copy (2026-08-30)Live source ↗
“At NC-1, about 35 MW of a contracted 40 MW IT deployment is operational; switchgear issues delayed full contracted run-rate billing beyond August.”
2026-11-03 · WhiteFiber (WYFI) Buys Two Data Center Sites for $60M; NC-1 Ramp Delayed - TradingView View cached copy (2026-11-04)Live source ↗Archive.org ↗
Checked November 9, 2026 against filings, releases and reporting published after the claim was made. Quotes are verbatim from the linked documents.
The claim, verbatim
NC-1 Phase 1 capacity will be delivered in two tranches: 20 MW in April 2026 and 20 MW in May 2026
Source (primary)
whitefiber 8-K exhibit (ea027401701ex99-1_white.htm) (SEC EDGAR (8-K Ex), press_release)
View cached copy (2026-09-21)Live source ↗
Quote: “20 MW expected in April 2026 and 20 MW expected in May 2026”
How we checked this
Checked on October 11, 2026. The cited source supports part of this claim, but not all of it.
The document gives the 20 MW April and 20 MW May 2026 timing, but it ties the 40 MW to Phase 1 and Phase 2 together, not to Phase 1 alone. It also presents the dates as expectations, not commitments.
Confirmed in the source:
- The 40 MW of NC-1 IT load for Nscale is expected as 20 MW in April 2026 and 20 MW in May 2026
We could not confirm this from the cited source:
- That the April and May 2026 tranches make up NC-1 Phase 1 capacity alone; the document says the 40 IT load MW covers Phase 1 & 2 combined
- That the capacity will be delivered on those dates, rather than being expected then
That does not mean it is false — only that this source does not establish it, as of the date above. If we find a source that settles it, we will re-check and update this page.
What we did: Read our cached copy of SEC EDGAR (8-K Ex) (https://www.sec.gov/Archives/edgar/data/2042022/000121390026007474/ea027401701ex99-1_white.htm) in full (23,241 characters, retrieved September 21, 2026) and checked each assertion in the claim against it.
Additional evidence
confirms whitefiber 8-K exhibit (ea027401701ex99-1_white.htm)
Quote: “20 MW expected in April 2026 and 20 MW expected in May 2026”