Muskie Data

Project of TeraWulf

Kind
campus
Location
Grayson, Kentucky
County
Carter
State/region
KY
Country
US
Status
announced as of October 16, 2026

Where it stands

TeraWulf acquired the roughly 285-acre Muskie site at EastPark near Grayson in May 2026. In October 2026 it amended its Kentucky Power agreement to double contracted capacity from 500 MW to 1 GW: phase 1 (500 MW) is to begin ramping in 2028 and phase 2 (500 MW) is pulled forward to 2029, pending Kentucky PSC approval. As of October 2026 the site was still described as a proposed site on a hayfield, and utility substation construction is scheduled to start in February 2027, so no data-center capacity is operating or under construction.

1,000 MW planned

PhaseMWStatusDateSource
Phase 1500plannedThe first 500 MW phase remains on track to begin ramping up in 2028.
2026-10-05 View cached copy (2026-10-06)Live source ↗Archive.org ↗
Phase 2500plannedaccelerates the delivery timeline for the project's second 500 MW phase, moving it to 2029 from the previously planned 2030.
2026-10-05 View cached copy (2026-10-06)Live source ↗Archive.org ↗

Assessed October 18, 2026 from the newest filings, releases and reporting that name this project (newest relied on: October 16, 2026).

Capacity

What has actually been delivered, against what has been promised. Each figure links to the statement it came from.

StageCapacityAs ofSource
Energized power flowing today--
Contracted a customer is on the hook1,000 MW2026-10-17Muskie Data Campus power agreement expanded to 1 GW
Under construction--
Permitted--
Interconnect approved utility has agreed to deliver500 MW2026-09-16Muskie utility service and transmission agreement
Interconnect requested in a queue, nothing approved--
Announced a press-release figure2,000 MW2026-10-10Muskie campus potential up to 2 GW

Claims about this project

2026-05-25 - stated
2026-05-25 - stated
2026-05-25 - stated
Additional 500 MW capacity targeted for H2 2030 500.0 MW. Promised by 2030-07-01.
2026-05-25 - stated
2026-05-26 - stated
Muskie May timetable: initial 500 MW H2 2028 500.0 MW. Promised by 2028-12-31.
2026-05-26 - stated
Muskie May timetable: second 500 MW H2 2030 500.0 MW. Promised by 2030-12-31.
2026-07-15 - stated
2026-08-04 - stated
Muskie Phase I Capacity 500.0 MW. Promised by 2028-12-31.
2026-08-04 - stated
Muskie second 500 MW phase 2030 500.0 MW. Promised by 2030-12-31.
2026-08-04 - stated
Muskie Phase I 500 MW ramp Q4 2028 500.0 MW. Promised by 2028-12-31.
2026-08-04 - stated
Muskie Data Phase II 500.0 MW. Promised by 2030-12-31.
2026-08-04 - stated
Muskie Data Phase I ramp 500.0 MW. Promised by 2028-12-31.
2026-08-04 - stated
Muskie Phase II Capacity 500.0 MW. Promised by 2030-12-31.
2026-08-19 - stated
Second 500 MW delivery at Muskie Data Campus 500.0 MW. Promised by 2030-07-01.
2026-08-19 - stated
First 500 MW ramp at Muskie Data Campus 500.0 MW. Promised by 2028-07-01.
2026-08-19 - stated
2026-08-21 - stated
Muskie campus 500 MW capacity by H2 2028 500.0 MW. Promised by 2028-12-31.
2026-08-21 - stated
Muskie campus 500 MW capacity by H2 2030 500.0 MW. Promised by 2030-12-31.
2026-09-15 - stated
Muskie Data Campus acquisition. Promised by 2028-10-01.
2026-09-15 - stated
Muskie Data Campus service start. Promised by 2028-10-01.
2026-09-16 - stated
Muskie utility service and transmission agreement 500.0 MW. Promised by 2028-12-31.
2026-10-03 - stated
2026-10-03 - stated
2026-10-04 - stated
Muskie second 500 MW phase accelerated to 2029 500.0 MW. Promised by 2029-12-31.
2026-10-04 - stated
2026-10-04 - stated
Muskie second 500 MW phase delivery moved to 2029 500.0 MW. Promised by 2029-12-31.
2026-10-04 - stated
Muskie first 500 MW phase ramp in 2028 500.0 MW. Promised by 2028-12-31.
2026-10-04 - stated
Muskie first 500 MW phase ramp targeted 2028 500.0 MW. Promised by 2028-12-31.
2026-10-05 - stated
Muskie second 500 MW phase moved to 2029 500.0 MW. Promised by 2029-12-31.
2026-10-05 - verified
Muskie phase 2 accelerated to 2029 500.0 MW. Promised by 2029-12-31.
2026-10-05 - stated
2026-10-05 - verified
2026-10-05 - stated
Muskie second 500-MW phase advanced to 2029 500.0 MW. Promised by 2029-12-31.
2026-10-05 - stated
2026-10-05 - verified
Muskie phase 1 (500 MW) to begin ramping in 2028 500.0 MW. Promised by 2028-12-31.
2026-10-05 - stated
2026-10-05 - stated
2026-10-05 - stated
Muskie phase 1 (500 MW) on track for H2 2028 500.0 MW. Promised by 2028-12-31.
2026-10-05 - verified
Muskie first 500 MW phase ramp in 2028 500.0 MW. Promised by 2028-12-31.
2026-10-05 - verified
2026-10-05 - stated
$100M residential bill credits funded by TeraWulf 100000000.0 USD. Promised by 2029-01-01.
2026-10-05 - verified
Muskie second 500 MW phase pulled forward to 2029 500.0 MW. Promised by 2029-12-31.
2026-10-05 - verified
2026-10-05 - stated
2026-10-05 - stated
2026-10-05 - stated
2026-10-06 - stated
Muskie initial 500 MW phase ramp in 2028 500.0 MW. Promised by 2028-12-31.
2026-10-06 - stated
2026-10-06 - stated
Muskie second 500 MW phase pulled forward to 2029 500.0 MW. Promised by 2029-12-31.
2026-10-06 - stated
2026-10-06 - stated
2026-10-06 - stated
2026-10-07 - stated
2026-10-07 - stated
2026-10-07 - stated
Muskie first 500 MW phase ramp targeted 2028 500.0 MW. Promised by 2028-12-31.
2026-10-07 - stated
Muskie second 500-MW phase accelerated to 2029 500.0 MW. Promised by 2029-12-31.
2026-10-07 - stated
2026-10-07 - stated
2026-10-07 - stated
Muskie second 500 MW phase pulled forward to 2029 500.0 MW. Promised by 2029-12-31.
2026-10-07 - stated
Muskie second 500 MW phase delivery moved to 2029 500.0 MW. Promised by 2029-12-31.
2026-10-07 - stated
2026-10-07 - stated
Muskie phase 1 (500 MW) ramp in 2028 500.0 MW. Promised by 2028-12-31.
2026-10-08 - stated
2026-10-08 - stated
2026-10-08 - stated
Muskie first 500 MW phase ramp in 2028 500.0 MW. Promised by 2028-12-31.
2026-10-08 - stated
2026-10-08 - stated
Muskie first phase ramp expected 2028. Promised by 2028-12-31.
2026-10-08 - stated
Muskie second 500 MW phase pulled forward to 2029 500.0 MW. Promised by 2029-12-31.
2026-10-08 - stated
2026-10-09 - stated
Muskie first 500 MW phase ramp in 2028 500.0 MW. Promised by 2028-12-31.
2026-10-09 - stated
Muskie second 500 MW phase accelerated to 2029 500.0 MW. Promised by 2029-12-31.
2026-10-09 - stated
2026-10-09 - stated
2026-10-09 - stated
Muskie Data Campus contracted power doubled to 1 GW 1000.0 MW. Promised by 2029-12-31.
2026-10-09 - stated
2026-10-09 - stated
Muskie second 500 MW phase advanced to 2029 500.0 MW. Promised by 2029-12-31.
2026-10-10 - stated
$100M residential winter bill credits funded by TeraWulf 100000000.0 USD. Promised by 2029-12-31.
2026-10-10 - stated
Muskie first 500 MW phase ramp in 2028 500.0 MW. Promised by 2028-12-31.
2026-10-10 - stated
2026-10-10 - stated
Muskie second 500 MW phase moved up to 2029 500.0 MW. Promised by 2029-12-31.
2026-10-10 - stated
Muskie first 500 MW phase to begin ramping in 2028 500.0 MW. Promised by 2028-12-31.
2026-10-10 - stated
2026-10-10 - stated
2026-10-10 - stated
Muskie second 500MW phase accelerated to 2029 500.0 MW. Promised by 2029-12-31.
2026-10-10 - stated
2026-10-10 - stated
2026-10-10 - stated
2026-10-10 - stated
Muskie second 500 MW phase pulled forward to 2029 500.0 MW. Promised by 2029-12-31.
2026-10-11 - stated
Muskie first 500 MW phase ramp in 2028 500.0 MW. Promised by 2028-12-31.
2026-10-11 - stated
Muskie second 500 MW phase pulled forward to 2029 500.0 MW. Promised by 2029-12-31.
2026-10-12 - stated
Muskie second 500 MW phase targeted for 2029 500.0 MW. Promised by 2029-12-31.
2026-10-12 - stated
Muskie first 500 MW phase to begin ramping in 2028 500.0 MW. Promised by 2028-12-31.
2026-10-12 - stated
Muskie Phase 1 (500 MW) ramp in 2028 500.0 MW. Promised by 2028-12-31.
2026-10-12 - stated
Muskie Phase 2 accelerated to 2029 500.0 MW. Promised by 2029-12-31.
2026-10-12 - stated
$100M residential winter bill credits funded by TeraWulf 100000000.0 USD. Promised by 2029-12-31.
2026-10-12 - stated
Muskie second 500 MW phase pulled forward to 2029 500.0 MW. Promised by 2029-12-31.
2026-10-12 - stated
2026-10-16 - stated
Muskie second 500 MW phase planned for 2029 500.0 MW. Promised by 2029-12-31.
2026-10-17 - stated
2026-10-17 - stated
Muskie second 500 MW phase planned for 2029 500.0 MW. Promised by 2029-12-31.

Site intelligence

Analytical estimate. Each site below is located from public records (filings, releases, news, OpenStreetMap) and checked against free satellite imagery; "How we located this site" lists every step and the score it earned. The conclusion is computed from night-time lights, surface heat and year-over-year change, with the dates it rests on. These are hypotheses under active tracking, not legal parcels or an official endorsement.
Grayson, Kentucky
Weak
Carter, KY
38.3326, -82.9485
Approximate address 110 E Main St, Grayson, KY 41143, USA Reverse-geocoded from the candidate centroid; not a permit-confirmed parcel address.
Conclusion so far We have not located the site yet. · confidence 30%
Undetermined: we have not yet located the actual site, only the town or county it is in, so imagery cannot say whether anything is running.
What would change this: A published address, parcel, coordinates or permit for the site itself.
Latest clear imagery: Google 2026-09-29
Newest clear images2 clear image date(s)
Visual view of terawulf-muskie-data, 2026-09-29 (Google Earth (wide view))
2026-09-29Google Earth (wide view) · 3.75 m/pixel
Visual view of terawulf-muskie-data, 2026-09-29 (Google Earth (close view))
2026-09-29Google Earth (close view) · 0.47 m/pixel
How we located this site
5/100 (weak): locality location 5
  1. Starting point (the project's stated locality) 2026-10-19
    Grayson, Kentucky → 38.33258, -82.94850 (locality)
  2. No site-level evidence yet 2026-10-19
    no address, road, landmark or coordinates tie this project to a specific parcel yet -- the town is shown, NOT the site