Muskie Data
Project of TeraWulf
Capacity
What has actually been delivered, against what has been promised. Each figure links to the statement it came from.
| Stage | Capacity | As of | Source |
|---|---|---|---|
| Energized power flowing today | -- | ||
| Contracted a customer is on the hook | -- | ||
| Under construction | -- | ||
| Permitted | -- | ||
| Interconnect approved utility has agreed to deliver | -- | ||
| Interconnect requested in a queue, nothing approved | -- | ||
| Announced a press-release figure | 2,000 MW | 2026-08-21 | CEO guidance to double Muskie Data Campus to 2 GW |
Claims about this project
2026-05-25 - stated
2026-05-25 - stated
2026-05-25 - stated
2026-05-25 - stated
2026-05-25 - stated
2026-05-25 - delayed
Transmission infrastructure and energy service agreements executed for Muskie Data Campus. Promised by 2026-05-22.
2026-08-21 - stated
2026-08-21 - stated
2026-08-21 - stated
2026-08-21 - stated
2026-08-21 - stated
2026-08-21 - stated
2026-09-01 - stated
2026-09-01 - stated