TeraWulf to pay financing costs of Big Sandy 760 MW plant
Company: TeraWulf - Project: Muskie Data
The claim, verbatim
The agreement requires TeraWulf to pay the estimated financing costs of Kentucky Power's planned 760-MW combined-cycle generation facility at Big Sandy, and includes collateral requirements.
Source (primary)
TeraWulf to double size of data center near Ashland; Ky. Power to add unit at Big Sandy - herald-dispatch.com (-, news_article)
View cached copy (2026-10-14)Live source ↗Archive.org ↗
Quote: “the agreement requires TeraWulf to pay the estimated financing costs associated with construction of Kentucky Power's planned 760-MW combined-cycle generation facility at the Big Sandy Power Plant”
How we checked this
Checked on October 16, 2026. The cited source supports every part of this claim.
Kentucky Power, as quoted in the article, says TeraWulf must pay the estimated financing costs of the planned 760-MW Big Sandy plant and that the agreement includes collateral requirements.
Confirmed in the source:
- The agreement requires TeraWulf to pay the estimated financing costs of Kentucky Power's planned 760-MW combined-cycle generation facility at the Big Sandy Power Plant
- The agreement includes collateral requirements
What we did: Read our cached copy of the publisher (https://www.herald-dispatch.com/business/terawulf-to-double-size-of-data-center-near-ashland-ky-power-to-add-unit-at/article_41decab0-682b-4b33-a8eb-f11987cbb3b3.html) in full (27,448 characters, retrieved October 14, 2026) and checked each assertion in the claim against it.
Additional evidence
confirms TeraWulf to double size of data center near Ashland; Ky. Power to add unit at Big Sandy - herald-dispatch.com
Quote: “the agreement requires TeraWulf to pay the estimated financing costs associated with construction of Kentucky Power's planned 760-MW combined-cycle generation facility at the Big Sandy Power Plant”