Muskie second 500 MW phase pulled forward to 2029
Company: TeraWulf - Project: Muskie Data
The claim, verbatim
Delivery of the second 500 MW phase at Muskie moved up to 2029 from 2030. This depends on Kentucky Public Service Commission approval and on Kentucky Power's construction schedule.
Source (primary)
TeraWulf Expands Kentucky Data Center Power Commitment to 1 GW - ConstructConnect News (-, news_article)
View cached copy (2026-10-15)Live source ↗Archive.org ↗
Quote: “The agreement also advances the planned delivery of the second 500-MW phase to 2029 from 2030.”
How we checked this
Checked on October 17, 2026. The cited source supports every part of this claim.
The article says the agreement advances the second 500-MW phase to 2029 from 2030, subject to Kentucky Public Service Commission approval and Kentucky Power's construction schedule.
Confirmed in the source:
- The amended Kentucky Power agreement moves planned delivery of the second 500 MW phase at the Muskie Data Campus up to 2029 from 2030.
- The 2029 timing for the second phase depends on approval by the Kentucky Public Service Commission.
- The 2029 timing for the second phase depends on Kentucky Power's construction schedule.
What we did: Read our cached copy of the publisher (https://news.constructconnect.com/terawulf-expands-kentucky-data-center-power-commitment-to-1-gw) in full (8,388 characters, retrieved October 15, 2026) and checked each assertion in the claim against it.
Additional evidence
confirms TeraWulf Expands Kentucky Data Center Power Commitment to 1 GW - ConstructConnect News
Quote: “The agreement also advances the planned delivery of the second 500-MW phase to 2029 from 2030.”