Kentucky Power amended electric demand agreement with TeraWulf (500 MW to 1 GW)
Company: TeraWulf - Project: Muskie Data
The claim, verbatim
Kentucky Power amended its agreement with TeraWulf to double contracted electric demand from 500 MW to 1 GW at the Muskie Data campus.
Source (primary)
Data center builders IREN, TeraWulf, and Core S... - Pluang (-, news_article)
View cached copy (2026-10-08)Live source ↗Archive.org ↗
Quote: “Kentucky Power has amended its agreement with TeraWulf to double the contracted electric demand from 500 MW to 1 GW at the Muskie Data campus in Kentucky”
How we checked this
Checked on October 13, 2026. The cited source supports every part of this claim.
A related-news summary on the page states that Kentucky Power amended its agreement with TeraWulf to double contracted electric demand from 500 MW to 1 GW at the Muskie Data campus in Kentucky.
Confirmed in the source:
- Kentucky Power amended its agreement with TeraWulf
- The amendment doubles contracted electric demand
- Contracted demand goes from 500 MW to 1 GW
- The agreement covers the Muskie Data campus
What we did: Read our cached copy of the publisher (https://pluang.com/en/news-feed/iren-turun-7-persen-saham-data-center-berbiaya-pembiayaan-tinggi-jatuh) in full (7,290 characters, retrieved October 8, 2026) and checked each assertion in the claim against it.
Additional evidence
confirms Data center builders IREN, TeraWulf, and Core S... - Pluang
Quote: “Kentucky Power has amended its agreement with TeraWulf to double the contracted electric demand from 500 MW to 1 GW at the Muskie Data campus in Kentucky”